Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 5 wards
8K+
Beneficiaries
5K female
KES 0.34B
Approved Budget
KES 0.04B allocated so far
707
Jobs Created
across all projects
9.57%
Goal Achievement
22 goals met
KES 43.8M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 230 projects
Budget Overview
Cost Estimate
KES 347.1M
Approved
KES 336.6M
Allocated
KES 43.8M
Utilized
KES 43.8M
Pending Bills
KES 3.5M
Utilization (utilized ÷ allocated)
100%
KES 43.8M of KES 43.8M allocated
Reach & Coverage
1
Sub-Counties
5
Wards Covered
4.5K
Female Beneficiaries
197
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 105.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 89.9M
Public Health And Medical Services
KES 68.6M
Education, Human Capital Development And Vocational Training
KES 50.3M
Governance, Administration, Communication And Devolution
KES 3.5M
Projects by Financial Year
Latest 8 of 11 years
Total: 230
Project Summary
Every tab adds up to the same 230 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 48 | 43 | 1 | 2 | 1 | 1 | KES 89,945,456.00 |
| Roads, Public Works, Transport And Infrastructure | 48 | 42 | 2 | 1 | 2 | 1 | KES 104,985,613.00 |
| Education, Human Capital Development And Vocational Training | 48 | 26 | 18 | 2 | 0 | 2 | KES 50,317,259.00 |
| Public Health And Medical Services | 29 | 26 | 0 | 3 | 0 | 0 | KES 68,649,023.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 2 | 2 | 0 | 0 | 0 | 0 | KES 1,355,190.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 2 | 2 | 0 | 0 | 0 | 0 | KES 0.00 |
| Governance, Administration, Communication And Devolution | 2 | 2 | 0 | 0 | 0 | 0 | KES 3,500,000.00 |
| No department assigned | 51 | 43 | 1 | 7 | 0 | 0 | KES 17,860,785.00 |
| Total | 230 | 186 | 22 | 15 | 3 | 4 | KES 336,613,326.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Rachuonyo South | 230 | 186 | 22 | 15 | 3 | 4 | KES 336,613,326.00 |
| Total | 230 | 186 | 22 | 15 | 3 | 4 | KES 336,613,326.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| South Kasipul | 49 | 38 | 7 | 3 | 1 | 0 | KES 86,085,093.00 |
| West Kasipul | 48 | 39 | 4 | 3 | 0 | 2 | KES 51,115,644.00 |
| Central Kasipul | 46 | 37 | 3 | 3 | 2 | 1 | KES 63,257,140.00 |
| East Kamagak | 44 | 37 | 4 | 2 | 0 | 1 | KES 49,511,917.00 |
| West Kamagak | 43 | 35 | 4 | 4 | 0 | 0 | KES 86,643,532.00 |
| Total | 230 | 186 | 22 | 15 | 3 | 4 | KES 336,613,326.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2025/2026 | 2 | 0 | 0 | 0 | 0 | 2 | KES 0.00 |
| FY2024/2025 | 52 | 26 | 22 | 3 | 0 | 1 | KES 51,590,027.00 |
| FY2023/2024 | 84 | 75 | 0 | 8 | 0 | 1 | KES 131,792,857.00 |
| FY2022/2023 | 61 | 57 | 0 | 4 | 0 | 0 | KES 99,056,091.00 |
| FY2020/2021 | 8 | 8 | 0 | 0 | 0 | 0 | KES 18,963,623.00 |
| FY2019/2020 | 7 | 7 | 0 | 0 | 0 | 0 | KES 3,718,600.00 |
| FY2018/2019 | 6 | 6 | 0 | 0 | 0 | 0 | KES 10,062,320.00 |
| FY2017/2018 | 1 | 1 | 0 | 0 | 0 | 0 | KES 500,000.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | 0 | KES 4,595,920.00 |
| FY2015/2016 | 5 | 2 | 0 | 0 | 3 | 0 | KES 6,155,490.00 |
| FY2014/2015 | 3 | 3 | 0 | 0 | 0 | 0 | KES 10,178,398.00 |
| Total | 230 | 186 | 22 | 15 | 3 | 4 | KES 336,613,326.00 |
All Projects
Browse and filter 230 county development projects