Homa Bay County Projects Monitoring Platform
Real-time transparency across 6 sub-counties · 13 wards
45
Total Projects
45 mapped on GIS
42
Completed
93% completion rate
2
Ongoing
active projects
7K+
Beneficiaries
1K female
KES 0.04B
Approved Budget
134.45% utilized
330
Jobs Created
across all projects
24.44%
Goal Achievement
11 goals met
13M
Total Spent
KES expenditure to date
Status Breakdown
42
Completed
2
Ongoing
1
Stalled
Budget Overview
Cost Estimate
KES 40.7M
Approved
KES 36.9M
Spent
KES 13.0M
Pending Bills
KES 0.0M
Overall utilization
134.45%
Reach & Coverage
6
Sub-Counties
13
Wards Covered
0.6K
Female Beneficiaries
45
GIS Mapped
Top Departments by Investment
Blue Economy, Fisheries, Mining And Digital Economy
KES 36.9M
Projects by Financial Year
7 financial years tracked
Total: 45
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Department | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Blue Economy, Fisheries, Mining And Digital Economy | 45 | 2 | 42 | 0 | 0 | 0 | 1 | 0 | 0 | KES 36,914,567.00 |
| Total | 45 | 2 | 42 | 0 | 0 | 0 | 1 | 0 | 0 | KES 36,914,567.00 |
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Suba North | 14 | 0 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | KES 9,282,966.00 |
| Suba South | 10 | 1 | 8 | 0 | 0 | 0 | 1 | 0 | 0 | KES 6,363,389.00 |
| Homa Bay Town | 7 | 0 | 7 | 0 | 0 | 0 | 0 | 0 | 0 | KES 11,928,777.00 |
| Rachuonyo North | 7 | 1 | 6 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,441,839.00 |
| Rangwe | 5 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 5,897,596.00 |
| Rachuonyo South | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Total | 45 | 2 | 42 | 0 | 0 | 0 | 1 | 0 | 0 | KES 36,914,567.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Kaksingri West | 6 | 1 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,237,313.00 |
| Mfangano Island | 5 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 1,548,914.00 |
| Kochia | 5 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 5,897,596.00 |
| Rusinga Island | 4 | 0 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,692,691.00 |
| Gembe | 3 | 0 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | KES 1,103,400.00 |
| West Karachuonyo | 3 | 1 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,441,839.00 |
| Kasgunga | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,937,961.00 |
| Gwassi North | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,828,274.00 |
| Gwassi South | 2 | 0 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | KES 297,802.00 |
| West Kamagak | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay Arujo | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,000,000.00 |
| Central Karachuonyo | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay East | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,000,000.00 |
| Total | 38 | 2 | 35 | 0 | 0 | 0 | 1 | 0 | 0 | KES 29,985,790.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2025/2026 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,888,360.00 |
| FY2024/2025 | 10 | 1 | 9 | 0 | 0 | 0 | 0 | 0 | 0 | KES 7,073,429.00 |
| FY2023/2024 | 19 | 0 | 18 | 0 | 0 | 0 | 1 | 0 | 0 | KES 20,154,827.00 |
| FY2022/2023 | 9 | 0 | 9 | 0 | 0 | 0 | 0 | 0 | 0 | KES 6,797,951.00 |
| FY2017/2018 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2012/2013 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Total | 43 | 2 | 40 | 0 | 0 | 0 | 1 | 0 | 0 | KES 36,914,567.00 |
All Projects
Browse and filter 45 county development projects