Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
49
Total Projects
36 mapped on GIS
38
Completed
78% completion rate
7
Ongoing
active projects
1K+
Beneficiaries
1K female
KES 0.09B
Approved Budget
100% utilized
103
Jobs Created
across all projects
6.12%
Goal Achievement
3 goals met
7M
Total Spent
KES expenditure to date
Status Breakdown
38
Completed
7
Ongoing
3
Stalled
1
Pending
Budget Overview
Cost Estimate
KES 88.5M
Approved
KES 86.1M
Spent
KES 7.3M
Pending Bills
KES 0.0M
Overall utilization
100%
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.7K
Female Beneficiaries
36
GIS Mapped
Top Departments by Investment
Public Health And Medical Services
KES 27.5M
Roads, Public Works, Transport And Infrastructure
KES 22.9M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 20.8M
Education, Human Capital Development And Vocational Training
KES 8.0M
Governance, Administration, Communication And Devolution
KES 3.5M
Projects by Financial Year
8 financial years tracked
Total: 49
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Department | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 12 | 1 | 8 | 0 | 0 | 1 | 2 | 0 | 0 | KES 20,800,000.00 |
| Public Health And Medical Services | 12 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | KES 27,535,436.00 |
| Education, Human Capital Development And Vocational Training | 8 | 4 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | KES 8,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 7 | 2 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 22,924,702.00 |
| Governance, Administration, Communication And Devolution | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 3,500,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 1,205,190.00 |
| Total | 42 | 7 | 32 | 0 | 0 | 1 | 2 | 0 | 0 | KES 83,965,328.00 |
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Rachuonyo South | 49 | 7 | 38 | 0 | 0 | 1 | 3 | 0 | 0 | KES 86,085,093.00 |
| Total | 49 | 7 | 38 | 0 | 0 | 1 | 3 | 0 | 0 | KES 86,085,093.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| South Kasipul | 49 | 7 | 38 | 0 | 0 | 1 | 3 | 0 | 0 | KES 86,085,093.00 |
| Total | 49 | 7 | 38 | 0 | 0 | 1 | 3 | 0 | 0 | KES 86,085,093.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2024/2025 | 14 | 7 | 6 | 0 | 0 | 0 | 1 | 0 | 0 | KES 20,097,939.00 |
| FY2023/2024 | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 20,550,000.00 |
| FY2022/2023 | 9 | 0 | 9 | 0 | 0 | 0 | 0 | 0 | 0 | KES 17,985,848.00 |
| FY2020/2021 | 3 | 0 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | KES 8,350,180.00 |
| FY2019/2020 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 4,595,920.00 |
| FY2015/2016 | 3 | 0 | 2 | 0 | 0 | 1 | 0 | 0 | 0 | KES 6,155,490.00 |
| FY2014/2015 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 8,349,716.00 |
| Total | 49 | 7 | 38 | 0 | 0 | 1 | 3 | 0 | 0 | KES 86,085,093.00 |
All Projects
Browse and filter 49 county development projects