Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
1K female
KES 0.09B
Approved Budget
KES 0.01B allocated so far
103
Jobs Created
across all projects
6.12%
Goal Achievement
3 goals met
KES 7.3M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 49 projects
Budget Overview
Cost Estimate
KES 88.5M
Approved
KES 86.1M
Allocated
KES 7.3M
Utilized
KES 7.3M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 7.3M of KES 7.3M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.7K
Female Beneficiaries
36
GIS Mapped
Top Departments by Investment
Public Health And Medical Services
KES 27.5M
Roads, Public Works, Transport And Infrastructure
KES 22.9M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 20.8M
Education, Human Capital Development And Vocational Training
KES 8.0M
Governance, Administration, Communication And Devolution
KES 3.5M
Projects by Financial Year
Latest 8 of 8 years
Total: 49
Project Summary
Every tab adds up to the same 49 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 12 | 8 | 1 | 2 | 1 | KES 20,800,000.00 |
| Public Health And Medical Services | 12 | 12 | 0 | 0 | 0 | KES 27,535,436.00 |
| Education, Human Capital Development And Vocational Training | 8 | 4 | 4 | 0 | 0 | KES 8,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 7 | 5 | 2 | 0 | 0 | KES 22,924,702.00 |
| Governance, Administration, Communication And Devolution | 2 | 2 | 0 | 0 | 0 | KES 3,500,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | KES 1,205,190.00 |
| No department assigned | 7 | 6 | 0 | 1 | 0 | KES 2,119,765.00 |
| Total | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo South | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
| Total | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| South Kasipul | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
| Total | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 14 | 6 | 7 | 1 | 0 | KES 20,097,939.00 |
| FY2023/2024 | 15 | 13 | 0 | 2 | 0 | KES 20,550,000.00 |
| FY2022/2023 | 9 | 9 | 0 | 0 | 0 | KES 17,985,848.00 |
| FY2020/2021 | 3 | 3 | 0 | 0 | 0 | KES 8,350,180.00 |
| FY2019/2020 | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | KES 4,595,920.00 |
| FY2015/2016 | 3 | 2 | 0 | 0 | 1 | KES 6,155,490.00 |
| FY2014/2015 | 2 | 2 | 0 | 0 | 0 | KES 8,349,716.00 |
| Total | 49 | 38 | 7 | 3 | 1 | KES 86,085,093.00 |
All Projects
Browse and filter 49 county development projects