Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.00B allocated so far
8
Jobs Created
across all projects
4.35%
Goal Achievement
3 goals met
KES 0.7M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 69 projects
Budget Overview
Cost Estimate
KES 24.4M
Approved
KES 24.4M
Allocated
KES 0.7M
Utilized
KES 0.7M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 0.7M of KES 0.7M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.2K
Female Beneficiaries
62
GIS Mapped
Top Departments by Investment
Education, Human Capital Development And Vocational Training
KES 7.0M
Roads, Public Works, Transport And Infrastructure
KES 5.9M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 1.9M
Lands, Physical Planning, Housing And Urban Development
KES 0.4M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.3M
Projects by Financial Year
Latest 8 of 11 years
· 4 with no year
Total: 69
Project Summary
Every tab adds up to the same 69 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 17 | 16 | 1 | 0 | 0 | 0 | KES 5,880,191.00 |
| Education, Human Capital Development And Vocational Training | 11 | 6 | 4 | 0 | 0 | 1 | KES 7,000,000.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 7 | 5 | 0 | 0 | 1 | 1 | KES 1,853,170.00 |
| Public Health And Medical Services | 6 | 4 | 0 | 1 | 0 | 1 | KES 0.00 |
| Governance, Administration, Communication And Devolution | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | 0 | KES 250,000.00 |
| Lands, Physical Planning, Housing And Urban Development | 1 | 1 | 0 | 0 | 0 | 0 | KES 420,000.00 |
| No department assigned | 25 | 22 | 2 | 1 | 0 | 0 | KES 9,031,947.00 |
| Total | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
| Total | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Kabuoch North | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
| Total | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2025/2026 | 6 | 4 | 2 | 0 | 0 | 0 | KES 3,500,000.00 |
| FY2024/2025 | 12 | 7 | 4 | 0 | 0 | 1 | KES 3,000,000.00 |
| FY2023/2024 | 21 | 17 | 0 | 2 | 0 | 2 | KES 12,480,755.00 |
| FY2022/2023 | 11 | 11 | 0 | 0 | 0 | 0 | KES 984,000.00 |
| FY2021/2022 | 2 | 2 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2020/2021 | 3 | 3 | 0 | 0 | 0 | 0 | KES 2,681,383.00 |
| FY2019/2020 | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2018/2019 | 4 | 4 | 0 | 0 | 0 | 0 | KES 369,170.00 |
| FY2017/2018 | 2 | 2 | 0 | 0 | 0 | 0 | KES 420,000.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | 0 | KES 250,000.00 |
| FY2015/2016 | 2 | 1 | 0 | 0 | 1 | 0 | KES 500,000.00 |
| No financial year recorded | 4 | 3 | 1 | 0 | 0 | 0 | KES 250,000.00 |
| Total | 69 | 56 | 7 | 2 | 1 | 3 | KES 24,435,308.00 |
All Projects
Browse and filter 69 county development projects