Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
210
Total Projects
185 mapped on GIS
165
Completed
79% completion rate
20
Ongoing
active projects
8K+
Beneficiaries
5K female
KES 0.65B
Approved Budget
99.58% utilized
306
Jobs Created
across all projects
9.52%
Goal Achievement
20 goals met
15M
Total Spent
KES expenditure to date
Status Breakdown
165
Completed
20
Ongoing
4
Stalled
3
Pending
Budget Overview
Cost Estimate KES 3,152.2M
Approved KES 651.5M
Spent KES 15.5M
Pending Bills KES 0.0M
Overall utilization
99.58%
Reach & Coverage
1
Sub-Counties
4
Wards Covered
5.1K
Female Beneficiaries
185
GIS Mapped
View on GIS Map
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 475.8M
Roads, Public Works, Transport And Infrastructure
KES 109.1M
Education, Human Capital Development And Vocational Training
KES 31.3M
Public Health And Medical Services
KES 21.3M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.3M
Projects by Financial Year
2012/
2013/
2014/
2015/
2016/
2017/
2018/
2019/
14 financial years tracked Total: 210
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
Department Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Roads, Public Works, Transport And Infrastructure 63 4 51 0 0 3 0 0 0 KES 109,093,650.00
Education, Human Capital Development And Vocational Training 40 15 25 0 0 0 0 0 0 KES 31,250,000.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 30 0 27 0 0 0 2 0 0 KES 475,776,771.00
Public Health And Medical Services 24 1 21 0 0 0 1 0 0 KES 21,265,902.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 4 0 4 0 0 0 0 0 0 KES 250,000.00
Total 161 20 128 0 0 3 3 0 0 KES 637,636,323.00
Sub-county Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Rachuonyo East 210 20 165 0 0 3 4 0 0 KES 651,499,299.00
Total 210 20 165 0 0 3 4 0 0 KES 651,499,299.00
Ward Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Kabondo East 5 0 5 0 0 0 0 0 0 KES 3,800,000.00
Kokwanyo/Kakelo 5 0 5 0 0 0 0 0 0 KES 3,800,000.00
Kojwach 4 0 4 0 0 0 0 0 0 KES 4,050,000.00
Kabondo West 3 0 3 0 0 0 0 0 0 KES 3,800,000.00
Total 17 0 17 0 0 0 0 0 0 KES 15,450,000.00
Financial Year Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
FY2025/2026 10 3 4 0 0 0 0 0 0 KES 163,357,600.00
FY2024/2025 60 17 36 0 0 0 1 0 0 KES 60,437,654.00
FY2023/2024 63 0 56 0 0 0 3 0 0 KES 72,678,960.00
FY2022/2023 25 0 23 0 0 0 0 0 0 KES 29,930,986.00
FY2021/2022 5 0 5 0 0 0 0 0 0 KES 8,698,564.00
FY2020/2021 8 0 8 0 0 0 0 0 0 KES 5,128,896.00
FY2019/2020 12 0 12 0 0 0 0 0 0 KES 295,371,819.00
FY2018/2019 4 0 4 0 0 0 0 0 0 KES 580,580.00
FY2017/2018 4 0 4 0 0 0 0 0 0 KES 0.00
FY2016/2017 4 0 4 0 0 0 0 0 0 KES 250,000.00
FY2015/2016 1 0 0 0 0 1 0 0 0 KES 0.00
FY2014/2015 1 0 0 0 0 1 0 0 0 KES 0.00
FY2013/2014 1 0 1 0 0 0 0 0 0 KES 0.00
FY2012/2013 1 0 0 0 0 1 0 0 0 KES 0.00
Total 199 20 157 0 0 3 4 0 0 KES 636,435,059.00
All Projects
Browse and filter 210 county development projects
Sub-county Projects: Rachuonyo East
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
210 results
Page 1 of 18