Homa Bay County Projects Monitoring Platform
Real-time transparency across 5 sub-counties · 6 wards
1K+
Beneficiaries
0K female
KES 0.06B
Approved Budget
KES 0.05B allocated so far
14
Jobs Created
across all projects
42.11%
Goal Achievement
8 goals met
KES 0.5M
Budget Utilized
0.94% of allocated
Status Breakdown
Adds up to all 19 projects
Budget Overview
Cost Estimate KES 59.9M
Approved KES 59.9M
Allocated KES 52.8M
Utilized KES 0.5M
Pending Bills KES 52.3M
Utilization (utilized ÷ allocated)
0.94%
KES 0.5M of KES 52.8M allocated
Reach & Coverage
5
Sub-Counties
6
Wards Covered
0.0K
Female Beneficiaries
6
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 42.2M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 5.9M
Public Health And Medical Services
KES 5.7M
Education, Human Capital Development And Vocational Training
KES 4.1M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 1.9M
Projects by Financial Year
13/14
Latest 1 of 1 years Total: 19
Project Summary
Every tab adds up to the same 19 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Water, Sanitation, Environment, Energy, Forestry And Climate Change 4 4 0 0 0 KES 5,887,482.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 4 3 0 0 1 KES 1,885,000.00
Roads, Public Works, Transport And Infrastructure 4 2 0 0 2 KES 42,234,252.00
Education, Human Capital Development And Vocational Training 3 3 0 0 0 KES 4,145,999.28
Public Health And Medical Services 3 3 0 0 0 KES 5,700,338.92
No department assigned 1 0 1 0 0 KES 0.00
Total 19 15 1 0 3 KES 59,853,072.20
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Ndhiwa 4 2 1 0 1 KES 5,446,096.00
Suba North 3 3 0 0 0 KES 748,000.00
Rangwe 2 1 0 0 1 KES 250,000.00
Rachuonyo East 1 1 0 0 0 KES 0.00
Rachuonyo North 1 0 0 0 1 KES 0.00
No sub-county recorded 8 8 0 0 0 KES 53,408,976.20
Total 19 15 1 0 3 KES 59,853,072.20
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Mfangano Island 2 2 0 0 0 KES 250,000.00
Kanyamwa Kalogi 2 1 0 0 1 KES 1,137,000.00
Gembe 1 1 0 0 0 KES 498,000.00
Kabuoch South 1 1 0 0 0 KES 4,309,096.00
Kendu Bay Town 1 0 0 0 1 KES 0.00
East Gem 1 0 0 0 1 KES 0.00
Ndhiwa – Sub-county-wide (no ward) 1 0 1 0 0 KES 0.00
Rachuonyo East – Sub-county-wide (no ward) 1 1 0 0 0 KES 0.00
Rangwe – Sub-county-wide (no ward) 1 1 0 0 0 KES 250,000.00
No sub-county or ward recorded 8 8 0 0 0 KES 53,408,976.20
Total 19 15 1 0 3 KES 59,853,072.20
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2013/2014 19 15 1 0 3 KES 59,853,072.20
Total 19 15 1 0 3 KES 59,853,072.20
All Projects
Browse and filter 19 county development projects
Loading…
19 results
Page 1 of 2