Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
3K+
Beneficiaries
2K female
KES 0.05B
Approved Budget
KES 0.01B allocated so far
295
Jobs Created
across all projects
36.54%
Goal Achievement
19 goals met
KES 15.3M
Budget Utilized
106.99% of allocated
Budget Overview
Cost Estimate
KES 51.8M
Approved
KES 51.3M
Allocated
KES 14.3M
Utilized
KES 15.3M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
106.99%
KES 15.3M of KES 14.3M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
1.8K
Female Beneficiaries
48
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 28.2M
Education, Human Capital Development And Vocational Training
KES 8.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 6.8M
Public Health And Medical Services
KES 5.0M
Blue Economy, Fisheries, Mining And Digital Economy
KES 3.2M
Projects by Financial Year
Latest 8 of 8 years
Total: 52
Project Summary
Every tab adds up to the same 52 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 14 | 13 | 0 | 1 | 0 | KES 28,248,942.00 |
| Education, Human Capital Development And Vocational Training | 14 | 11 | 3 | 0 | 0 | KES 8,000,000.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 10 | 10 | 0 | 0 | 0 | KES 6,792,069.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 6 | 5 | 1 | 0 | 0 | KES 3,237,313.00 |
| Public Health And Medical Services | 3 | 2 | 0 | 1 | 0 | KES 5,008,530.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| No department assigned | 4 | 2 | 1 | 1 | 0 | KES 0.00 |
| Total | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
| Total | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Kaksingri West | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
| Total | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2025/2026 | 7 | 3 | 4 | 0 | 0 | KES 6,888,360.00 |
| FY2024/2025 | 11 | 9 | 1 | 1 | 0 | KES 2,000,000.00 |
| FY2023/2024 | 12 | 12 | 0 | 0 | 0 | KES 7,727,906.00 |
| FY2022/2023 | 15 | 13 | 0 | 2 | 0 | KES 24,769,989.00 |
| FY2020/2021 | 1 | 1 | 0 | 0 | 0 | KES 1,100,000.00 |
| FY2017/2018 | 4 | 4 | 0 | 0 | 0 | KES 5,292,069.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2012/2013 | 1 | 1 | 0 | 0 | 0 | KES 3,508,530.00 |
| Total | 52 | 44 | 5 | 3 | 0 | KES 51,286,854.00 |
All Projects
Browse and filter 52 county development projects