Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
52
Total Projects
50 mapped on GIS
41
Completed
79% completion rate
5
Ongoing
active projects
1K+
Beneficiaries
0K female
KES 0.04B
Approved Budget
100% utilized
42
Jobs Created
across all projects
9.62%
Goal Achievement
5 goals met
4M
Total Spent
KES expenditure to date
Status Breakdown
41
Completed
5
Ongoing
Budget Overview
Cost Estimate KES 38.3M
Approved KES 38.3M
Spent KES 3.5M
Pending Bills KES 0.0M
Overall utilization
100%
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.4K
Female Beneficiaries
50
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 24.1M
Education, Human Capital Development And Vocational Training
KES 9.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 3.5M
Blue Economy, Fisheries, Mining And Digital Economy
KES 0.0M
Public Health And Medical Services
KES 0.0M
Projects by Financial Year
2017/
2018/
2019/
2021/
2022/
2023/
2024/
2025/
8 financial years tracked Total: 52
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
Department Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Roads, Public Works, Transport And Infrastructure 21 0 19 0 0 0 0 0 0 KES 24,086,749.00
Education, Human Capital Development And Vocational Training 9 2 6 0 0 0 0 0 0 KES 9,000,000.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 5 0 5 0 0 0 0 0 0 KES 3,500,000.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 2 0 2 0 0 0 0 0 0 KES 0.00
Blue Economy, Fisheries, Mining And Digital Economy 1 0 1 0 0 0 0 0 0 KES 0.00
Public Health And Medical Services 1 0 1 0 0 0 0 0 0 KES 0.00
Total 39 2 34 0 0 0 0 0 0 KES 36,586,749.00
Sub-county Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Rachuonyo North 52 5 41 0 0 0 0 0 0 KES 38,330,749.00
Total 52 5 41 0 0 0 0 0 0 KES 38,330,749.00
Ward Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Central Karachuonyo 52 5 41 0 0 0 0 0 0 KES 38,330,749.00
Total 52 5 41 0 0 0 0 0 0 KES 38,330,749.00
Financial Year Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
FY2025/2026 3 2 1 0 0 0 0 0 0 KES 3,000,000.00
FY2024/2025 9 1 6 0 0 0 0 0 0 KES 9,553,412.00
FY2023/2024 15 2 12 0 0 0 0 0 0 KES 19,309,753.00
FY2022/2023 13 0 12 0 0 0 0 0 0 KES 5,718,184.00
FY2021/2022 1 0 1 0 0 0 0 0 0 KES 500,000.00
FY2019/2020 1 0 1 0 0 0 0 0 0 KES 0.00
FY2018/2019 2 0 2 0 0 0 0 0 0 KES 0.00
FY2017/2018 2 0 2 0 0 0 0 0 0 KES 0.00
Total 46 5 37 0 0 0 0 0 0 KES 38,081,349.00
All Projects
Browse and filter 52 county development projects
Ward Projects: Central Karachuonyo
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
52 results
Page 1 of 5