Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
0K female
KES 0.28B
Approved Budget
KES 0.00B allocated so far
18
Jobs Created
across all projects
9.62%
Goal Achievement
5 goals met
KES 3.5M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 52 projects
Budget Overview
Cost Estimate
KES 280.4M
Approved
KES 280.1M
Allocated
KES 3.5M
Utilized
KES 3.5M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 3.5M of KES 3.5M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.3K
Female Beneficiaries
36
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 236.2M
Roads, Public Works, Transport And Infrastructure
KES 26.8M
Education, Human Capital Development And Vocational Training
KES 8.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 1.1M
Public Health And Medical Services
KES 0.0M
Projects by Financial Year
Latest 8 of 10 years
Total: 52
Project Summary
Every tab adds up to the same 52 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 17 | 6 | 2 | 0 | 0 | 9 | KES 26,826,818.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 10 | 9 | 0 | 0 | 0 | 1 | KES 236,246,374.00 |
| Education, Human Capital Development And Vocational Training | 7 | 4 | 3 | 0 | 0 | 0 | KES 8,000,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 4 | 3 | 0 | 0 | 1 | 0 | KES 1,137,000.00 |
| Public Health And Medical Services | 3 | 3 | 0 | 0 | 0 | 0 | KES 0.00 |
| No department assigned | 11 | 8 | 0 | 0 | 0 | 3 | KES 7,896,702.00 |
| Total | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
| Total | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Kanyamwa Kalogi | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
| Total | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2027/2028 | 1 | 0 | 0 | 0 | 0 | 1 | KES 0.00 |
| FY2025/2026 | 4 | 1 | 0 | 0 | 0 | 3 | KES 227,450,000.00 |
| FY2024/2025 | 8 | 0 | 5 | 0 | 0 | 3 | KES 3,000,000.00 |
| FY2023/2024 | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| FY2022/2023 | 17 | 13 | 0 | 0 | 0 | 4 | KES 16,359,608.00 |
| FY2020/2021 | 3 | 2 | 0 | 0 | 0 | 1 | KES 10,352,304.00 |
| FY2019/2020 | 2 | 2 | 0 | 0 | 0 | 0 | KES 3,496,374.00 |
| FY2018/2019 | 4 | 4 | 0 | 0 | 0 | 0 | KES 1,309,362.00 |
| FY2017/2018 | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2013/2014 | 2 | 1 | 0 | 0 | 1 | 0 | KES 1,137,000.00 |
| Total | 52 | 33 | 5 | 0 | 1 | 13 | KES 280,106,894.00 |
All Projects
Browse and filter 52 county development projects