Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
49
Total Projects
43 mapped on GIS
38
Completed
78% completion rate
5
Ongoing
active projects
2K+
Beneficiaries
1K female
KES 0.05B
Approved Budget
229.36% utilized
73
Jobs Created
across all projects
10.2%
Goal Achievement
5 goals met
9M
Total Spent
KES expenditure to date
Status Breakdown
38
Completed
5
Ongoing
4
Stalled
Budget Overview
Cost Estimate
KES 47.2M
Approved
KES 46.9M
Spent
KES 8.7M
Pending Bills
KES 0.0M
Overall utilization
229.36%
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.9K
Female Beneficiaries
43
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 23.8M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 5.3M
Public Health And Medical Services
KES 4.5M
Education, Human Capital Development And Vocational Training
KES 2.7M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Projects by Financial Year
8 financial years tracked
Total: 49
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Department | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 12 | 0 | 11 | 0 | 0 | 0 | 1 | 0 | 0 | KES 23,799,660.00 |
| Education, Human Capital Development And Vocational Training | 10 | 4 | 6 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,701,924.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 7 | 1 | 5 | 0 | 0 | 0 | 1 | 0 | 0 | KES 5,300,000.00 |
| Public Health And Medical Services | 4 | 0 | 3 | 0 | 0 | 0 | 1 | 0 | 0 | KES 4,475,338.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Total | 34 | 5 | 26 | 0 | 0 | 0 | 3 | 0 | 0 | KES 36,276,922.00 |
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Rachuonyo North | 49 | 5 | 38 | 0 | 0 | 0 | 4 | 0 | 0 | KES 46,884,104.00 |
| Total | 49 | 5 | 38 | 0 | 0 | 0 | 4 | 0 | 0 | KES 46,884,104.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Kibiri | 49 | 5 | 38 | 0 | 0 | 0 | 4 | 0 | 0 | KES 46,884,104.00 |
| Total | 49 | 5 | 38 | 0 | 0 | 0 | 4 | 0 | 0 | KES 46,884,104.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2025/2026 | 9 | 5 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | KES 9,245,688.00 |
| FY2024/2025 | 3 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2023/2024 | 20 | 0 | 17 | 0 | 0 | 0 | 3 | 0 | 0 | KES 13,996,234.00 |
| FY2022/2023 | 11 | 0 | 9 | 0 | 0 | 0 | 1 | 0 | 0 | KES 19,166,844.00 |
| FY2021/2022 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2020/2021 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 4,475,338.00 |
| FY2019/2020 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2018/2019 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 0.00 |
| Total | 49 | 5 | 38 | 0 | 0 | 0 | 4 | 0 | 0 | KES 46,884,104.00 |
All Projects
Browse and filter 49 county development projects