Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
66
Total Projects
56 mapped on GIS
50
Completed
76% completion rate
6
Ongoing
active projects
2K+
Beneficiaries
1K female
KES 0.06B
Approved Budget
99.28% utilized
138
Jobs Created
across all projects
9.09%
Goal Achievement
6 goals met
12M
Total Spent
KES expenditure to date
Status Breakdown
50
Completed
6
Ongoing
5
Stalled
2
Pending
Budget Overview
Cost Estimate KES 62.6M
Approved KES 62.6M
Spent KES 11.8M
Pending Bills KES 1.0M
Overall utilization
99.28%
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.8K
Female Beneficiaries
56
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 30.4M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 16.2M
Education, Human Capital Development And Vocational Training
KES 11.3M
Public Health And Medical Services
KES 3.4M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.3M
Projects by Financial Year
2012/
2014/
2016/
2018/
2020/
2022/
2023/
2024/
8 financial years tracked Total: 66
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
Department Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Roads, Public Works, Transport And Infrastructure 21 1 16 0 0 1 2 0 0 KES 30,435,209.00
Public Health And Medical Services 12 0 11 0 0 0 1 0 0 KES 3,434,539.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 11 0 9 0 0 0 1 0 0 KES 16,200,000.00
Education, Human Capital Development And Vocational Training 11 4 6 0 0 1 0 0 0 KES 11,300,000.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 1 0 1 0 0 0 0 0 0 KES 250,000.00
Total 56 5 43 0 0 2 4 0 0 KES 61,619,748.00
Sub-county Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Ndhiwa 66 6 50 0 0 2 5 0 0 KES 62,619,748.00
Total 66 6 50 0 0 2 5 0 0 KES 62,619,748.00
Ward Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
Kanyamwa Kosewe 66 6 50 0 0 2 5 0 0 KES 62,619,748.00
Total 66 6 50 0 0 2 5 0 0 KES 62,619,748.00
Financial Year Total Projects Ongoing Completed Pending Pending Planned Stalled Delayed Canceled Total Money
FY2024/2025 7 4 0 0 0 0 2 0 0 KES 4,000,000.00
FY2023/2024 26 2 23 0 0 0 1 0 0 KES 38,113,829.00
FY2022/2023 22 0 20 0 0 0 2 0 0 KES 15,571,380.00
FY2020/2021 1 0 0 0 0 0 0 0 0 KES 0.00
FY2018/2019 2 0 2 0 0 0 0 0 0 KES 0.00
FY2016/2017 3 0 3 0 0 0 0 0 0 KES 1,500,000.00
FY2014/2015 2 0 1 0 0 1 0 0 0 KES 3,434,539.00
FY2012/2013 1 0 0 0 0 1 0 0 0 KES 0.00
Total 64 6 49 0 0 2 5 0 0 KES 62,619,748.00
All Projects
Browse and filter 66 county development projects
Ward Projects: Kanyamwa Kosewe
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
66 results
Page 1 of 6