Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 0 wards
2K+
Beneficiaries
1K female
KES 0.06B
Approved Budget
KES 0.01B allocated so far
122
Jobs Created
across all projects
9.23%
Goal Achievement
6 goals met
KES 7.5M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 65 projects
Budget Overview
Cost Estimate
KES 63.5M
Approved
KES 63.5M
Allocated
KES 7.5M
Utilized
KES 7.5M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 7.5M of KES 7.5M allocated
Reach & Coverage
1
Sub-Counties
0
Wards Covered
1.0K
Female Beneficiaries
53
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 27.4M
Roads, Public Works, Transport And Infrastructure
KES 16.9M
Public Health And Medical Services
KES 12.7M
Education, Human Capital Development And Vocational Training
KES 5.0M
Projects by Financial Year
Latest 8 of 10 years
Total: 65
Project Summary
Every tab adds up to the same 65 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 21 | 15 | 3 | 1 | 0 | 2 | KES 16,934,352.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 15 | 14 | 0 | 0 | 0 | 1 | KES 27,440,295.00 |
| Education, Human Capital Development And Vocational Training | 13 | 7 | 4 | 0 | 1 | 1 | KES 5,000,000.00 |
| Public Health And Medical Services | 6 | 5 | 0 | 0 | 0 | 1 | KES 12,672,466.00 |
| No department assigned | 10 | 5 | 3 | 2 | 0 | 0 | KES 1,499,708.00 |
| Total | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
| Total | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa – Sub-county-wide (no ward) | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
| Total | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2025/2026 | 5 | 2 | 0 | 0 | 0 | 3 | KES 0.00 |
| FY2024/2025 | 14 | 6 | 7 | 1 | 0 | 0 | KES 2,000,000.00 |
| FY2023/2024 | 25 | 21 | 1 | 2 | 0 | 1 | KES 35,089,399.00 |
| FY2022/2023 | 11 | 9 | 1 | 0 | 0 | 1 | KES 8,371,890.00 |
| FY2020/2021 | 4 | 4 | 0 | 0 | 0 | 0 | KES 13,501,137.00 |
| FY2019/2020 | 1 | 1 | 0 | 0 | 0 | 0 | KES 3,588,850.00 |
| FY2017/2018 | 2 | 2 | 0 | 0 | 0 | 0 | KES 995,545.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| FY2013/2014 | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2012/2013 | 1 | 0 | 0 | 0 | 1 | 0 | KES 0.00 |
| Total | 65 | 46 | 10 | 3 | 1 | 5 | KES 63,546,821.00 |
All Projects
Browse and filter 65 county development projects