Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
2K+
Beneficiaries
1K female
KES 0.06B
Approved Budget
KES 0.01B allocated so far
193
Jobs Created
across all projects
16.22%
Goal Achievement
6 goals met
KES 7.5M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 52.0M
Approved
KES 56.5M
Allocated
KES 7.5M
Utilized
KES 7.5M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 7.5M of KES 7.5M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
1.4K
Female Beneficiaries
29
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 25.7M
Roads, Public Works, Transport And Infrastructure
KES 14.0M
Education, Human Capital Development And Vocational Training
KES 7.0M
Public Health And Medical Services
KES 4.1M
Projects by Financial Year
Latest 7 of 7 years
Total: 37
Project Summary
Every tab adds up to the same 37 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 11 | 11 | 0 | 0 | 0 | KES 25,672,331.00 |
| Roads, Public Works, Transport And Infrastructure | 7 | 7 | 0 | 0 | 0 | KES 13,951,767.00 |
| Education, Human Capital Development And Vocational Training | 6 | 6 | 0 | 0 | 0 | KES 7,000,000.00 |
| Public Health And Medical Services | 2 | 2 | 0 | 0 | 0 | KES 4,133,042.00 |
| No department assigned | 11 | 11 | 0 | 0 | 0 | KES 5,750,000.00 |
| Total | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo South | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
| Total | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Central Kasipul | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
| Total | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 3 | 3 | 0 | 0 | 0 | KES 4,500,000.00 |
| FY2023/2024 | 18 | 18 | 0 | 0 | 0 | KES 28,839,447.00 |
| FY2022/2023 | 10 | 10 | 0 | 0 | 0 | KES 10,000,000.00 |
| FY2020/2021 | 2 | 2 | 0 | 0 | 0 | KES 5,632,898.00 |
| FY2019/2020 | 2 | 2 | 0 | 0 | 0 | KES 2,972,475.00 |
| FY2018/2019 | 1 | 1 | 0 | 0 | 0 | KES 4,062,320.00 |
| FY2017/2018 | 1 | 1 | 0 | 0 | 0 | KES 500,000.00 |
| Total | 37 | 37 | 0 | 0 | 0 | KES 56,507,140.00 |
All Projects
Browse and filter 37 county development projects