Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
8K+
Beneficiaries
5K female
KES 0.59B
Approved Budget
KES 0.02B allocated so far
306
Jobs Created
across all projects
11.83%
Goal Achievement
20 goals met
KES 15.4M
Budget Utilized
99.58% of allocated
Budget Overview
Cost Estimate
KES 3,099.0M
Approved
KES 587.9M
Allocated
KES 15.5M
Utilized
KES 15.4M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
99.58%
KES 15.4M of KES 15.5M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
5.1K
Female Beneficiaries
150
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 469.8M
Roads, Public Works, Transport And Infrastructure
KES 69.8M
Public Health And Medical Services
KES 21.3M
Education, Human Capital Development And Vocational Training
KES 16.3M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.3M
Projects by Financial Year
Latest 8 of 12 years
· 8 with no year
Total: 169
Project Summary
Every tab adds up to the same 169 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 51 | 51 | 0 | 0 | 0 | KES 69,815,031.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 28 | 28 | 0 | 0 | 0 | KES 469,776,771.00 |
| Education, Human Capital Development And Vocational Training | 25 | 25 | 0 | 0 | 0 | KES 16,250,000.00 |
| Public Health And Medical Services | 21 | 21 | 0 | 0 | 0 | KES 21,265,902.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 4 | 4 | 0 | 0 | 0 | KES 250,000.00 |
| No department assigned | 40 | 40 | 0 | 0 | 0 | KES 10,568,755.00 |
| Total | 169 | 169 | 0 | 0 | 0 | KES 587,926,459.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo East | 169 | 169 | 0 | 0 | 0 | KES 587,926,459.00 |
| Total | 169 | 169 | 0 | 0 | 0 | KES 587,926,459.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Kabondo East | 5 | 5 | 0 | 0 | 0 | KES 3,800,000.00 |
| Kokwanyo/Kakelo | 5 | 5 | 0 | 0 | 0 | KES 3,800,000.00 |
| Kojwach | 4 | 4 | 0 | 0 | 0 | KES 4,050,000.00 |
| Kabondo West | 3 | 3 | 0 | 0 | 0 | KES 3,800,000.00 |
| Rachuonyo East – Sub-county-wide (no ward) | 152 | 152 | 0 | 0 | 0 | KES 572,476,459.00 |
| Total | 169 | 169 | 0 | 0 | 0 | KES 587,926,459.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2026/2027 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2025/2026 | 4 | 4 | 0 | 0 | 0 | KES 160,357,600.00 |
| FY2024/2025 | 37 | 37 | 0 | 0 | 0 | KES 19,049,660.00 |
| FY2023/2024 | 58 | 58 | 0 | 0 | 0 | KES 63,806,854.00 |
| FY2022/2023 | 23 | 23 | 0 | 0 | 0 | KES 28,682,486.00 |
| FY2021/2022 | 5 | 5 | 0 | 0 | 0 | KES 8,698,564.00 |
| FY2020/2021 | 8 | 8 | 0 | 0 | 0 | KES 5,128,896.00 |
| FY2019/2020 | 12 | 12 | 0 | 0 | 0 | KES 295,371,819.00 |
| FY2018/2019 | 4 | 4 | 0 | 0 | 0 | KES 580,580.00 |
| FY2017/2018 | 4 | 4 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 4 | 4 | 0 | 0 | 0 | KES 250,000.00 |
| FY2013/2014 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| No financial year recorded | 8 | 8 | 0 | 0 | 0 | KES 6,000,000.00 |
| Total | 169 | 169 | 0 | 0 | 0 | KES 587,926,459.00 |
All Projects
Browse and filter 169 county development projects