Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 5 wards
8K+
Beneficiaries
5K female
KES 0.29B
Approved Budget
KES 0.04B allocated so far
707
Jobs Created
across all projects
11.83%
Goal Achievement
22 goals met
KES 43.8M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 186 projects
Budget Overview
Cost Estimate KES 289.5M
Approved KES 287.1M
Allocated KES 43.8M
Utilized KES 43.8M
Pending Bills KES 3.5M
Utilization (utilized ÷ allocated)
100%
KES 43.8M of KES 43.8M allocated
Reach & Coverage
1
Sub-Counties
5
Wards Covered
4.5K
Female Beneficiaries
160
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 93.4M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 81.9M
Public Health And Medical Services
KES 62.1M
Education, Human Capital Development And Vocational Training
KES 29.3M
Governance, Administration, Communication And Devolution
KES 3.5M
Projects by Financial Year
16/17
17/18
18/19
19/20
20/21
22/23
23/24
24/25
Latest 8 of 10 years Total: 186
Project Summary
Every tab adds up to the same 186 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Water, Sanitation, Environment, Energy, Forestry And Climate Change 43 43 0 0 0 KES 81,945,456.00
Roads, Public Works, Transport And Infrastructure 42 42 0 0 0 KES 93,444,139.00
Education, Human Capital Development And Vocational Training 26 26 0 0 0 KES 29,317,259.00
Public Health And Medical Services 26 26 0 0 0 KES 62,149,023.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 2 2 0 0 0 KES 1,355,190.00
Blue Economy, Fisheries, Mining And Digital Economy 2 2 0 0 0 KES 0.00
Governance, Administration, Communication And Devolution 2 2 0 0 0 KES 3,500,000.00
No department assigned 43 43 0 0 0 KES 15,360,785.00
Total 186 186 0 0 0 KES 287,071,852.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Rachuonyo South 186 186 0 0 0 KES 287,071,852.00
Total 186 186 0 0 0 KES 287,071,852.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
West Kasipul 39 39 0 0 0 KES 44,615,644.00
South Kasipul 38 38 0 0 0 KES 67,337,132.00
East Kamagak 37 37 0 0 0 KES 41,511,917.00
Central Kasipul 37 37 0 0 0 KES 56,507,140.00
West Kamagak 35 35 0 0 0 KES 77,100,019.00
Total 186 186 0 0 0 KES 287,071,852.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2024/2025 26 26 0 0 0 KES 16,548,553.00
FY2023/2024 75 75 0 0 0 KES 120,292,857.00
FY2022/2023 57 57 0 0 0 KES 96,056,091.00
FY2020/2021 8 8 0 0 0 KES 18,963,623.00
FY2019/2020 7 7 0 0 0 KES 3,718,600.00
FY2018/2019 6 6 0 0 0 KES 10,062,320.00
FY2017/2018 1 1 0 0 0 KES 500,000.00
FY2016/2017 1 1 0 0 0 KES 4,595,920.00
FY2015/2016 2 2 0 0 0 KES 6,155,490.00
FY2014/2015 3 3 0 0 0 KES 10,178,398.00
Total 186 186 0 0 0 KES 287,071,852.00
All Projects
Browse and filter 186 county development projects
Sub-county Projects: Rachuonyo South
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
186 results
Page 1 of 16