Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
10K+
Beneficiaries
3K female
KES 0.20B
Approved Budget
KES 0.04B allocated so far
1,022
Jobs Created
across all projects
14.29%
Goal Achievement
29 goals met
KES 18.8M
Budget Utilized
41.94% of allocated
Status Breakdown
Adds up to all 203 projects
Budget Overview
Cost Estimate KES 200.6M
Approved KES 200.6M
Allocated KES 44.9M
Utilized KES 18.8M
Pending Bills KES 7.0M
Utilization (utilized ÷ allocated)
41.94%
KES 18.8M of KES 44.9M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
2.6K
Female Beneficiaries
186
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 119.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 36.4M
Education, Human Capital Development And Vocational Training
KES 26.6M
Blue Economy, Fisheries, Mining And Digital Economy
KES 5.9M
Public Health And Medical Services
KES 5.0M
Projects by Financial Year
18/19
19/20
20/21
21/22
22/23
23/24
24/25
25/26
Latest 8 of 12 years · 1 with no year Total: 203
Project Summary
Every tab adds up to the same 203 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Roads, Public Works, Transport And Infrastructure 72 72 0 0 0 KES 118,975,849.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 46 46 0 0 0 KES 36,438,425.00
Education, Human Capital Development And Vocational Training 24 24 0 0 0 KES 26,552,330.00
Public Health And Medical Services 13 13 0 0 0 KES 5,001,543.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 8 8 0 0 0 KES 250,000.00
Blue Economy, Fisheries, Mining And Digital Economy 5 5 0 0 0 KES 5,897,596.00
No department assigned 35 35 0 0 0 KES 7,456,648.00
Total 203 203 0 0 0 KES 200,572,391.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Rangwe 203 203 0 0 0 KES 200,572,391.00
Total 203 203 0 0 0 KES 200,572,391.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Kochia 83 83 0 0 0 KES 70,120,925.00
East Gem 41 41 0 0 0 KES 46,175,917.00
West Gem 39 39 0 0 0 KES 38,323,452.00
Kagan 4 4 0 0 0 KES 7,597,520.00
Rangwe – Sub-county-wide (no ward) 36 36 0 0 0 KES 38,354,577.00
Total 203 203 0 0 0 KES 200,572,391.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2025/2026 8 8 0 0 0 KES 3,000,000.00
FY2024/2025 33 33 0 0 0 KES 38,523,891.00
FY2023/2024 75 75 0 0 0 KES 77,297,438.00
FY2022/2023 47 47 0 0 0 KES 44,894,626.00
FY2021/2022 2 2 0 0 0 KES 11,847,312.00
FY2020/2021 7 7 0 0 0 KES 10,945,084.00
FY2019/2020 7 7 0 0 0 KES 4,244,670.00
FY2018/2019 9 9 0 0 0 KES 1,450,000.00
FY2017/2018 9 9 0 0 0 KES 1,110,650.00
FY2016/2017 3 3 0 0 0 KES 0.00
FY2014/2015 1 1 0 0 0 KES 7,008,720.00
FY2013/2014 1 1 0 0 0 KES 250,000.00
No financial year recorded 1 1 0 0 0 KES 0.00
Total 203 203 0 0 0 KES 200,572,391.00
All Projects
Browse and filter 203 county development projects
Sub-county Projects: Rangwe
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
203 results
Page 1 of 17