Homa Bay County Projects Monitoring Platform
Real-time transparency across 6 sub-counties · 13 wards
7K+
Beneficiaries
1K female
KES 0.03B
Approved Budget
KES 0.01B allocated so far
330
Jobs Created
across all projects
26.19%
Goal Achievement
11 goals met
KES 13.1M
Budget Utilized
134.45% of allocated
Status Breakdown
Adds up to all 42 projects
Budget Overview
Cost Estimate KES 31.3M
Approved KES 30.7M
Allocated KES 9.7M
Utilized KES 13.1M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
134.45%
KES 13.1M of KES 9.7M allocated
Reach & Coverage
6
Sub-Counties
13
Wards Covered
0.6K
Female Beneficiaries
42
GIS Mapped
View on GIS Map
Top Departments by Investment
Blue Economy, Fisheries, Mining And Digital Economy
KES 30.7M
Projects by Financial Year
12/13
16/17
17/18
22/23
23/24
24/25
Latest 6 of 6 years · 2 with no year Total: 42
Project Summary
Every tab adds up to the same 42 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Blue Economy, Fisheries, Mining And Digital Economy 42 42 0 0 0 KES 30,735,714.00
Total 42 42 0 0 0 KES 30,735,714.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Suba North 14 14 0 0 0 KES 9,282,966.00
Suba South 8 8 0 0 0 KES 3,177,227.00
Homa Bay Town 7 7 0 0 0 KES 11,928,777.00
Rachuonyo North 6 6 0 0 0 KES 449,148.00
Rangwe 5 5 0 0 0 KES 5,897,596.00
Rachuonyo South 2 2 0 0 0 KES 0.00
Total 42 42 0 0 0 KES 30,735,714.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Kaksingri West 5 5 0 0 0 KES 348,953.00
Mfangano Island 5 5 0 0 0 KES 1,548,914.00
Kochia 5 5 0 0 0 KES 5,897,596.00
Rusinga Island 4 4 0 0 0 KES 3,692,691.00
Gembe 3 3 0 0 0 KES 1,103,400.00
West Karachuonyo 2 2 0 0 0 KES 449,148.00
Kasgunga 2 2 0 0 0 KES 2,937,961.00
Gwassi North 2 2 0 0 0 KES 2,828,274.00
West Kamagak 2 2 0 0 0 KES 0.00
Homa Bay Arujo 2 2 0 0 0 KES 2,000,000.00
Central Karachuonyo 1 1 0 0 0 KES 0.00
Gwassi South 1 1 0 0 0 KES 0.00
Homa Bay East 1 1 0 0 0 KES 3,000,000.00
Homa Bay Town – Sub-county-wide (no ward) 4 4 0 0 0 KES 6,928,777.00
Rachuonyo North – Sub-county-wide (no ward) 3 3 0 0 0 KES 0.00
Total 42 42 0 0 0 KES 30,735,714.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2024/2025 9 9 0 0 0 KES 4,080,738.00
FY2023/2024 18 18 0 0 0 KES 19,857,025.00
FY2022/2023 9 9 0 0 0 KES 6,797,951.00
FY2017/2018 2 2 0 0 0 KES 0.00
FY2016/2017 1 1 0 0 0 KES 0.00
FY2012/2013 1 1 0 0 0 KES 0.00
No financial year recorded 2 2 0 0 0 KES 0.00
Total 42 42 0 0 0 KES 30,735,714.00
All Projects
Browse and filter 42 county development projects
Department Projects: Blue Economy, Fisheries, Mining And Digital Economy
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
42 results
Page 1 of 4