Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.01B allocated so far
67
Jobs Created
across all projects
38.46%
Goal Achievement
5 goals met
KES 6.0M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 25.4M
Approved
KES 24.9M
Allocated
KES 6.0M
Utilized
KES 6.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 6.0M of KES 6.0M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.2K
Female Beneficiaries
13
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 21.7M
Public Health And Medical Services
KES 3.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Department Of Agriculture, Irrigation And Livestock Development
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 13
Project Summary
Every tab adds up to the same 13 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 5 | 3 | 2 | 0 | 0 | KES 21,658,042.00 |
| Public Health And Medical Services | 2 | 0 | 0 | 2 | 0 | KES 3,000,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| Department Of Agriculture, Irrigation And Livestock Development | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| No department assigned | 4 | 4 | 0 | 0 | 0 | KES 250,000.00 |
| Total | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Total | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Gwassi South | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Total | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
| Total | 13 | 9 | 2 | 2 | 0 | KES 24,908,042.00 |
All Projects
Browse and filter 13 county development projects