Homa Bay County Projects Monitoring Platform
Real-time transparency across 8 sub-counties · 29 wards
7K+
Beneficiaries
0K female
KES 0.28B
Approved Budget
KES 0.04B allocated so far
280
Jobs Created
across all projects
12.3%
Goal Achievement
15 goals met
KES 104.7M
Budget Utilized
256.73% of allocated
Status Breakdown
Adds up to all 122 projects
Budget Overview
Cost Estimate
KES 275.4M
Approved
KES 279.5M
Allocated
KES 40.8M
Utilized
KES 104.7M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
256.73%
KES 104.7M of KES 40.8M allocated
Reach & Coverage
8
Sub-Counties
29
Wards Covered
0.2K
Female Beneficiaries
114
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 279.5M
Projects by Financial Year
Latest 1 of 1 years
Total: 122
Project Summary
Every tab adds up to the same 122 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
| Total | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 20 | 8 | 6 | 3 | 0 | 3 | KES 5,367,315.00 |
| Rachuonyo East | 18 | 11 | 5 | 0 | 0 | 2 | KES 39,149,008.00 |
| Rachuonyo North | 18 | 6 | 10 | 0 | 0 | 2 | KES 34,958,407.00 |
| Rachuonyo South | 15 | 11 | 2 | 1 | 0 | 1 | KES 16,524,472.00 |
| Rangwe | 13 | 8 | 1 | 0 | 0 | 4 | KES 33,233,200.00 |
| Homa Bay Town | 11 | 7 | 2 | 0 | 0 | 2 | KES 95,105,810.00 |
| Suba South | 10 | 7 | 2 | 1 | 0 | 0 | KES 21,658,042.00 |
| Suba North | 9 | 7 | 2 | 0 | 0 | 0 | KES 33,480,695.00 |
| No sub-county recorded | 8 | 0 | 7 | 0 | 0 | 1 | KES 0.00 |
| Total | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Kendu Bay Town | 7 | 0 | 6 | 0 | 0 | 1 | KES 20,523,202.00 |
| West Kasipul | 7 | 7 | 0 | 0 | 0 | 0 | KES 0.00 |
| Central Karachuonyo | 6 | 4 | 1 | 0 | 0 | 1 | KES 8,553,412.00 |
| Kochia | 6 | 5 | 0 | 0 | 0 | 1 | KES 12,169,516.00 |
| Gwassi South | 5 | 3 | 2 | 0 | 0 | 0 | KES 21,658,042.00 |
| Mfangano Island | 5 | 3 | 2 | 0 | 0 | 0 | KES 18,647,542.00 |
| East Gem | 5 | 1 | 1 | 0 | 0 | 3 | KES 8,994,196.00 |
| Kabuoch North | 5 | 4 | 1 | 0 | 0 | 0 | KES 0.00 |
| Kanyamwa Kalogi | 5 | 0 | 2 | 0 | 0 | 3 | KES 0.00 |
| Rusinga Island | 3 | 3 | 0 | 0 | 0 | 0 | KES 9,344,397.00 |
| East Kamagak | 3 | 2 | 0 | 0 | 0 | 1 | KES 0.00 |
| Kanyamwa Kosewe | 2 | 0 | 0 | 2 | 0 | 0 | KES 0.00 |
| Kaksingri West | 2 | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| West Kamagak | 2 | 1 | 0 | 1 | 0 | 0 | KES 9,776,511.00 |
| South Kasipul | 2 | 0 | 2 | 0 | 0 | 0 | KES 6,747,961.00 |
| Ruma Kaksingri | 2 | 2 | 0 | 0 | 0 | 0 | KES 0.00 |
| Kabondo East | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Kanyaluo | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay Central | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Central Kasipul | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| North Karuochonyo | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Kanyadoto | 1 | 0 | 1 | 0 | 0 | 0 | KES 5,367,315.00 |
| Homa Bay East | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Gwassi North | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay Arujo | 1 | 0 | 1 | 0 | 0 | 0 | KES 70,000,000.00 |
| Kibiri | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| West Karachuonyo | 1 | 0 | 1 | 0 | 0 | 0 | KES 5,881,793.00 |
| Kasgunga | 1 | 1 | 0 | 0 | 0 | 0 | KES 5,488,756.00 |
| West Gem | 1 | 1 | 0 | 0 | 0 | 0 | KES 5,569,488.00 |
| Rachuonyo East – Sub-county-wide (no ward) | 17 | 10 | 5 | 0 | 0 | 2 | KES 39,149,008.00 |
| Homa Bay Town – Sub-county-wide (no ward) | 8 | 5 | 1 | 0 | 0 | 2 | KES 25,105,810.00 |
| Ndhiwa – Sub-county-wide (no ward) | 7 | 4 | 2 | 1 | 0 | 0 | KES 0.00 |
| Rangwe – Sub-county-wide (no ward) | 1 | 1 | 0 | 0 | 0 | 0 | KES 6,500,000.00 |
| Rachuonyo North – Sub-county-wide (no ward) | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| No sub-county or ward recorded | 8 | 0 | 7 | 0 | 0 | 1 | KES 0.00 |
| Total | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2024/2025 | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
| Total | 122 | 65 | 37 | 5 | 0 | 15 | KES 279,476,949.00 |
All Projects
Browse and filter 122 county development projects