Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.00B allocated so far
18
Jobs Created
across all projects
10%
Goal Achievement
1 goals met
KES 3.5M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 17.0M
Approved
KES 17.0M
Allocated
KES 3.5M
Utilized
KES 3.5M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 3.5M of KES 3.5M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.3K
Female Beneficiaries
10
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 6.2M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 3.5M
Education, Human Capital Development And Vocational Training
KES 3.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 10
Project Summary
Every tab adds up to the same 10 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 3 | 3 | 0 | 0 | 0 | 0 | KES 3,500,000.00 |
| Education, Human Capital Development And Vocational Training | 3 | 3 | 0 | 0 | 0 | 0 | KES 3,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 2 | 2 | 0 | 0 | 0 | 0 | KES 6,205,846.00 |
| No department assigned | 2 | 1 | 0 | 0 | 0 | 1 | KES 4,296,400.00 |
| Total | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Total | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Kanyamwa Kalogi | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Total | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2023/2024 | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
| Total | 10 | 9 | 0 | 0 | 0 | 1 | KES 17,002,246.00 |
All Projects
Browse and filter 10 county development projects