Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
1K female
KES 0.02B
Approved Budget
KES 0.00B allocated so far
89
Jobs Created
across all projects
20%
Goal Achievement
3 goals met
KES 3.8M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 23.0M
Approved
KES 23.0M
Allocated
KES 3.8M
Utilized
KES 3.8M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 3.8M of KES 3.8M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.8K
Female Beneficiaries
15
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 10.8M
Education, Human Capital Development And Vocational Training
KES 5.0M
Roads, Public Works, Transport And Infrastructure
KES 4.2M
Public Health And Medical Services
KES 3.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 15
Project Summary
Every tab adds up to the same 15 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 5 | 5 | 0 | 0 | 0 | KES 10,800,000.00 |
| Education, Human Capital Development And Vocational Training | 5 | 4 | 0 | 1 | 0 | KES 5,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 4 | 4 | 0 | 0 | 0 | KES 4,231,372.00 |
| Public Health And Medical Services | 1 | 0 | 0 | 1 | 0 | KES 3,000,000.00 |
| Total | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo South | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Total | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| East Kamagak | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Total | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2023/2024 | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
| Total | 15 | 13 | 0 | 2 | 0 | KES 23,031,372.00 |
All Projects
Browse and filter 15 county development projects