Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
15
Total Projects
15 mapped on GIS
13
Completed
87% completion rate
0
Ongoing
active projects
1K+
Beneficiaries
1K female
KES 0.02B
Approved Budget
100% utilized
89
Jobs Created
across all projects
20%
Goal Achievement
3 goals met
4M
Total Spent
KES expenditure to date
Status Breakdown
13
Completed
2
Stalled
Budget Overview
Cost Estimate
KES 23.0M
Approved
KES 23.0M
Spent
KES 3.8M
Pending Bills
KES 0.0M
Overall utilization
100%
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.8K
Female Beneficiaries
15
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 10.8M
Education, Human Capital Development And Vocational Training
KES 5.0M
Roads, Public Works, Transport And Infrastructure
KES 4.2M
Public Health And Medical Services
KES 3.0M
Projects by Financial Year
1 financial years tracked
Total: 15
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Department | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 5 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 10,800,000.00 |
| Education, Human Capital Development And Vocational Training | 5 | 0 | 4 | 0 | 0 | 0 | 1 | 0 | 0 | KES 5,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 4 | 0 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | KES 4,231,372.00 |
| Public Health And Medical Services | 1 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | KES 3,000,000.00 |
| Total | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Rachuonyo South | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Total | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| East Kamagak | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Total | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2023/2024 | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
| Total | 15 | 0 | 13 | 0 | 0 | 0 | 2 | 0 | 0 | KES 23,031,372.00 |
All Projects
Browse and filter 15 county development projects