Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
1K female
KES 0.01B
Approved Budget
KES 0.00B allocated so far
102
Jobs Created
across all projects
15.38%
Goal Achievement
2 goals met
KES 3.7M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 14.4M
Approved
KES 10.7M
Allocated
KES 3.7M
Utilized
KES 3.7M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 3.7M of KES 3.7M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.7K
Female Beneficiaries
12
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 6.7M
Public Health And Medical Services
KES 3.5M
Blue Economy, Fisheries, Mining And Digital Economy
KES 0.3M
Roads, Public Works, Transport And Infrastructure
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 13
Project Summary
Every tab adds up to the same 13 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 6 | 6 | 0 | 0 | 0 | KES 6,650,000.00 |
| Roads, Public Works, Transport And Infrastructure | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Public Health And Medical Services | 1 | 1 | 0 | 0 | 0 | KES 3,500,000.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 1 | 0 | 0 | 1 | 0 | KES 297,802.00 |
| No department assigned | 3 | 3 | 0 | 0 | 0 | KES 250,000.00 |
| Total | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Total | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Gwassi South | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Total | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2023/2024 | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
| Total | 13 | 12 | 0 | 1 | 0 | KES 10,697,802.00 |
All Projects
Browse and filter 13 county development projects