Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
4K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.01B allocated so far
179
Jobs Created
across all projects
44.44%
Goal Achievement
8 goals met
KES 5.7M
Budget Utilized
109.59% of allocated
Budget Overview
Cost Estimate
KES 20.4M
Approved
KES 20.4M
Allocated
KES 5.2M
Utilized
KES 5.7M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
109.59%
KES 5.7M of KES 5.2M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.1K
Female Beneficiaries
17
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 9.1M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 4.2M
Public Health And Medical Services
KES 3.0M
Education, Human Capital Development And Vocational Training
KES 2.4M
Blue Economy, Fisheries, Mining And Digital Economy
KES 0.8M
Projects by Financial Year
Latest 1 of 1 years
Total: 18
Project Summary
Every tab adds up to the same 18 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 4 | 4 | 0 | 0 | 0 | 0 | KES 9,064,898.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 3 | 1 | 1 | 0 | 0 | 1 | KES 4,150,000.00 |
| Education, Human Capital Development And Vocational Training | 3 | 2 | 1 | 0 | 0 | 0 | KES 2,400,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 3 | 3 | 0 | 0 | 0 | 0 | KES 749,182.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 2 | 2 | 0 | 0 | 0 | 0 | KES 750,000.00 |
| Public Health And Medical Services | 1 | 1 | 0 | 0 | 0 | 0 | KES 3,000,000.00 |
| No department assigned | 2 | 1 | 0 | 0 | 0 | 1 | KES 250,000.00 |
| Total | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Suba North | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Total | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Mfangano Island | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Total | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2023/2024 | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
| Total | 18 | 14 | 2 | 0 | 0 | 2 | KES 20,364,080.00 |
All Projects
Browse and filter 18 county development projects