Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
3K+
Beneficiaries
0K female
KES 0.03B
Approved Budget
KES 0.01B allocated so far
332
Jobs Created
across all projects
15.79%
Goal Achievement
6 goals met
KES 0.3M
Budget Utilized
4.24% of allocated
Budget Overview
Cost Estimate KES 33.3M
Approved KES 33.3M
Allocated KES 7.1M
Utilized KES 0.3M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
4.24%
KES 0.3M of KES 7.1M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.5K
Female Beneficiaries
37
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 11.3M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 9.6M
Education, Human Capital Development And Vocational Training
KES 6.0M
Blue Economy, Fisheries, Mining And Digital Economy
KES 5.9M
Projects by Financial Year
23/24
Latest 1 of 1 years Total: 38
Project Summary
Every tab adds up to the same 38 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Not set Total Money
Roads, Public Works, Transport And Infrastructure 16 13 0 2 0 1 KES 11,277,571.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 6 6 0 0 0 0 KES 9,599,855.00
Education, Human Capital Development And Vocational Training 6 6 0 0 0 0 KES 6,000,000.00
Blue Economy, Fisheries, Mining And Digital Economy 5 5 0 0 0 0 KES 5,897,596.00
No department assigned 5 3 1 1 0 0 KES 500,000.00
Total 38 33 1 3 0 1 KES 33,275,022.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Not set Total Money
Rangwe 38 33 1 3 0 1 KES 33,275,022.00
Total 38 33 1 3 0 1 KES 33,275,022.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Not set Total Money
Kochia 38 33 1 3 0 1 KES 33,275,022.00
Total 38 33 1 3 0 1 KES 33,275,022.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Not set Total Money
FY2023/2024 38 33 1 3 0 1 KES 33,275,022.00
Total 38 33 1 3 0 1 KES 33,275,022.00
All Projects
Browse and filter 38 county development projects
Ward Projects: Kochia
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
38 results
Page 1 of 4