Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
1K+
Beneficiaries
0K female
KES 0.03B
Approved Budget
KES 0.00B allocated so far
28
Jobs Created
across all projects
7.14%
Goal Achievement
1 goals met
KES 27.0M
Budget Utilized
672.02% of allocated
Budget Overview
Cost Estimate
KES 29.9M
Approved
KES 28.6M
Allocated
KES 4.0M
Utilized
KES 27.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
672.02%
KES 27.0M of KES 4.0M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.3K
Female Beneficiaries
12
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 26.1M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 1.5M
Blue Economy, Fisheries, Mining And Digital Economy
KES 1.0M
Education, Human Capital Development And Vocational Training
KES 0.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 14
Project Summary
Every tab adds up to the same 14 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 6 | 5 | 0 | 0 | 1 | KES 26,095,281.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 3 | 2 | 0 | 0 | 1 | KES 1,497,480.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 3 | 0 | 2 | 0 | 1 | KES 0.00 |
| Education, Human Capital Development And Vocational Training | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 1 | 1 | 0 | 0 | 0 | KES 1,000,000.00 |
| Total | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Homa Bay Town | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Total | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Homa Bay Arujo | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Total | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2023/2024 | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
| Total | 14 | 8 | 3 | 0 | 3 | KES 28,592,761.00 |
All Projects
Browse and filter 14 county development projects