Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
6K+
Beneficiaries
3K female
KES 0.09B
Approved Budget
KES 0.02B allocated so far
560
Jobs Created
across all projects
16.09%
Goal Achievement
14 goals met
KES 11.7M
Budget Utilized
63.3% of allocated
Status Breakdown
Adds up to all 87 projects
Budget Overview
Cost Estimate
KES 92.8M
Approved
KES 92.8M
Allocated
KES 18.5M
Utilized
KES 11.7M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
63.3%
KES 11.7M of KES 18.5M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
2.6K
Female Beneficiaries
83
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 40.4M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 21.7M
Education, Human Capital Development And Vocational Training
KES 21.0M
Blue Economy, Fisheries, Mining And Digital Economy
KES 5.9M
Public Health And Medical Services
KES 2.5M
Projects by Financial Year
Latest 1 of 1 years
Total: 87
Project Summary
Every tab adds up to the same 87 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 30 | 26 | 1 | 2 | 0 | 1 | KES 40,369,632.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 23 | 22 | 0 | 1 | 0 | 0 | KES 21,749,855.00 |
| Education, Human Capital Development And Vocational Training | 16 | 15 | 1 | 0 | 0 | 0 | KES 21,000,000.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 5 | 5 | 0 | 0 | 0 | 0 | KES 5,897,596.00 |
| Public Health And Medical Services | 2 | 1 | 1 | 0 | 0 | 0 | KES 2,486,453.00 |
| No department assigned | 11 | 6 | 4 | 1 | 0 | 0 | KES 1,249,018.00 |
| Total | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Rangwe | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
| Total | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Kochia | 38 | 33 | 1 | 3 | 0 | 1 | KES 33,275,022.00 |
| East Gem | 15 | 15 | 0 | 0 | 0 | 0 | KES 18,950,745.00 |
| West Gem | 13 | 12 | 1 | 0 | 0 | 0 | KES 18,665,395.00 |
| Kagan | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Rangwe – Sub-county-wide (no ward) | 20 | 15 | 4 | 1 | 0 | 0 | KES 21,861,392.00 |
| Total | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2023/2024 | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
| Total | 87 | 75 | 7 | 4 | 0 | 1 | KES 92,752,554.00 |
All Projects
Browse and filter 87 county development projects