Homa Bay County Projects Monitoring Platform
Real-time transparency across 8 sub-counties · 26 wards
0K+
Beneficiaries
0K female
KES 0.05B
Approved Budget
KES 0.00B allocated so far
0
Jobs Created
across all projects
0%
Goal Achievement
0 goals met
KES 0.0M
Budget Utilized
0% of allocated
Status Breakdown
Adds up to all 127 projects
Budget Overview
Cost Estimate
KES 44.2M
Approved
KES 45.3M
Allocated
KES 0.0M
Utilized
KES 0.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 0.0M allocated
Reach & Coverage
8
Sub-Counties
26
Wards Covered
0.0K
Female Beneficiaries
118
GIS Mapped
Top Departments by Investment
No department data available.
Projects by Financial Year
Latest 1 of 1 years
Total: 127
Project Summary
Every tab adds up to the same 127 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| No department assigned | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
| Total | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ndhiwa | 24 | 18 | 1 | 4 | 0 | 1 | KES 20,578,075.00 |
| Rachuonyo North | 22 | 14 | 4 | 1 | 0 | 3 | KES 10,336,449.00 |
| Suba South | 20 | 18 | 2 | 0 | 0 | 0 | KES 2,522,000.00 |
| Rachuonyo East | 15 | 11 | 0 | 1 | 0 | 3 | KES 4,289,450.00 |
| Rachuonyo South | 12 | 8 | 0 | 4 | 0 | 0 | KES 2,993,020.00 |
| Rangwe | 11 | 6 | 4 | 1 | 0 | 0 | KES 1,249,018.00 |
| Suba North | 6 | 3 | 0 | 1 | 0 | 2 | KES 1,348,000.00 |
| Homa Bay Town | 6 | 4 | 0 | 0 | 0 | 2 | KES 997,489.00 |
| No sub-county recorded | 11 | 1 | 6 | 0 | 0 | 4 | KES 995,860.00 |
| Total | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Ruma Kaksingri | 15 | 14 | 1 | 0 | 0 | 0 | KES 2,272,000.00 |
| Kabuoch North | 8 | 7 | 0 | 1 | 0 | 0 | KES 7,031,947.00 |
| Kochia | 5 | 3 | 1 | 1 | 0 | 0 | KES 500,000.00 |
| Kanyamwa Kosewe | 4 | 3 | 1 | 0 | 0 | 0 | KES 500,000.00 |
| Central Karachuonyo | 4 | 0 | 3 | 0 | 0 | 1 | KES 994,600.00 |
| Kibiri | 4 | 3 | 0 | 1 | 0 | 0 | KES 1,011,900.00 |
| North Karuochonyo | 4 | 4 | 0 | 0 | 0 | 0 | KES 0.00 |
| Central Kasipul | 4 | 3 | 0 | 1 | 0 | 0 | KES 1,250,000.00 |
| Kendu Bay Town | 3 | 1 | 1 | 0 | 0 | 1 | KES 3,954,020.00 |
| West Kasipul | 3 | 2 | 0 | 1 | 0 | 0 | KES 500,000.00 |
| West Kamagak | 3 | 2 | 0 | 1 | 0 | 0 | KES 993,020.00 |
| Gwassi South | 3 | 3 | 0 | 0 | 0 | 0 | KES 250,000.00 |
| Gembe | 2 | 1 | 0 | 1 | 0 | 0 | KES 748,000.00 |
| Kabuoch South | 2 | 1 | 0 | 1 | 0 | 0 | KES 6,500,000.00 |
| West Karachuonyo | 2 | 2 | 0 | 0 | 0 | 0 | KES 0.00 |
| Kanyadoto | 2 | 2 | 0 | 0 | 0 | 0 | KES 750,000.00 |
| Kanyamwa Kalogi | 2 | 1 | 0 | 0 | 0 | 1 | KES 4,296,400.00 |
| East Gem | 2 | 2 | 0 | 0 | 0 | 0 | KES 499,850.00 |
| Mfangano Island | 2 | 1 | 0 | 0 | 0 | 1 | KES 250,000.00 |
| South Kasipul | 2 | 1 | 0 | 1 | 0 | 0 | KES 250,000.00 |
| Lambwe | 1 | 1 | 0 | 0 | 0 | 0 | KES 250,000.00 |
| Gwassi North | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Kanyikela | 1 | 1 | 0 | 0 | 0 | 0 | KES 250,000.00 |
| Kaksingri West | 1 | 1 | 0 | 0 | 0 | 0 | KES 0.00 |
| Rusinga Island | 1 | 0 | 0 | 0 | 0 | 1 | KES 100,000.00 |
| Kagan | 1 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Rachuonyo East – Sub-county-wide (no ward) | 15 | 11 | 0 | 1 | 0 | 3 | KES 4,289,450.00 |
| Homa Bay Town – Sub-county-wide (no ward) | 6 | 4 | 0 | 0 | 0 | 2 | KES 997,489.00 |
| Ndhiwa – Sub-county-wide (no ward) | 5 | 3 | 0 | 2 | 0 | 0 | KES 1,249,728.00 |
| Rachuonyo North – Sub-county-wide (no ward) | 5 | 4 | 0 | 0 | 0 | 1 | KES 4,375,929.00 |
| Rangwe – Sub-county-wide (no ward) | 3 | 1 | 2 | 0 | 0 | 0 | KES 249,168.00 |
| No sub-county or ward recorded | 11 | 1 | 6 | 0 | 0 | 4 | KES 995,860.00 |
| Total | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2023/2024 | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
| Total | 127 | 83 | 17 | 12 | 0 | 15 | KES 45,309,361.00 |
All Projects
Browse and filter 127 county development projects