Homa Bay County Projects Monitoring Platform
Real-time transparency across 5 sub-counties · 9 wards
6K+
Beneficiaries
2K female
KES 0.00B
Approved Budget
KES 0.00B allocated so far
295
Jobs Created
across all projects
70%
Goal Achievement
14 goals met
KES 4.9M
Budget Utilized
125.66% of allocated
Budget Overview
Cost Estimate
KES 5.9M
Approved
KES 5.0M
Allocated
KES 3.9M
Utilized
KES 4.9M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
125.66%
KES 4.9M of KES 3.9M allocated
Reach & Coverage
5
Sub-Counties
9
Wards Covered
1.8K
Female Beneficiaries
20
GIS Mapped
Top Departments by Investment
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 5.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 20
Project Summary
Every tab adds up to the same 20 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
| Total | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba North | 7 | 7 | 0 | 0 | 0 | KES 1,849,182.00 |
| Homa Bay Town | 5 | 3 | 0 | 0 | 2 | KES 1,747,489.00 |
| Suba South | 5 | 5 | 0 | 0 | 0 | KES 0.00 |
| Rachuonyo South | 1 | 1 | 0 | 0 | 0 | KES 150,000.00 |
| Rachuonyo East | 1 | 1 | 0 | 0 | 0 | KES 250,000.00 |
| No sub-county recorded | 1 | 1 | 0 | 0 | 0 | KES 995,860.00 |
| Total | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Ruma Kaksingri | 5 | 5 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay Arujo | 3 | 2 | 0 | 0 | 1 | KES 1,497,480.00 |
| Mfangano Island | 3 | 3 | 0 | 0 | 0 | KES 749,182.00 |
| Gembe | 2 | 2 | 0 | 0 | 0 | KES 750,000.00 |
| West Kamagak | 1 | 1 | 0 | 0 | 0 | KES 150,000.00 |
| Lambwe | 1 | 1 | 0 | 0 | 0 | KES 250,000.00 |
| Kojwach | 1 | 1 | 0 | 0 | 0 | KES 250,000.00 |
| Homa Bay East | 1 | 1 | 0 | 0 | 0 | KES 250,009.00 |
| Rusinga Island | 1 | 1 | 0 | 0 | 0 | KES 100,000.00 |
| Homa Bay Town – Sub-county-wide (no ward) | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| No sub-county or ward recorded | 1 | 1 | 0 | 0 | 0 | KES 995,860.00 |
| Total | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2023/2024 | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
| Total | 20 | 18 | 0 | 0 | 2 | KES 4,992,531.00 |
All Projects