Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 5 wards
0K+
Beneficiaries
0K female
KES 0.10B
Approved Budget
KES 0.01B allocated so far
100
Jobs Created
across all projects
1.64%
Goal Achievement
1 goals met
KES 14.1M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 61 projects
Budget Overview
Cost Estimate KES 99.1M
Approved KES 99.1M
Allocated KES 14.1M
Utilized KES 14.1M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 14.1M of KES 14.1M allocated
Reach & Coverage
1
Sub-Counties
5
Wards Covered
0.1K
Female Beneficiaries
60
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 43.3M
Public Health And Medical Services
KES 27.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 12.5M
Education, Human Capital Development And Vocational Training
KES 9.0M
Projects by Financial Year
22/23
Latest 1 of 1 years Total: 61
Project Summary
Every tab adds up to the same 61 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Roads, Public Works, Transport And Infrastructure 13 13 0 0 0 KES 43,288,304.00
Public Health And Medical Services 12 11 0 1 0 KES 27,000,000.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 6 6 0 0 0 KES 12,500,000.00
Education, Human Capital Development And Vocational Training 5 4 0 1 0 KES 9,000,000.00
No department assigned 25 23 0 2 0 KES 7,267,787.00
Total 61 57 0 4 0 KES 99,056,091.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Rachuonyo South 61 57 0 4 0 KES 99,056,091.00
Total 61 57 0 4 0 KES 99,056,091.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
East Kamagak 18 18 0 0 0 KES 15,250,000.00
West Kasipul 13 11 0 2 0 KES 19,577,949.00
Central Kasipul 11 10 0 1 0 KES 10,250,000.00
West Kamagak 10 9 0 1 0 KES 35,992,294.00
South Kasipul 9 9 0 0 0 KES 17,985,848.00
Total 61 57 0 4 0 KES 99,056,091.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2022/2023 61 57 0 4 0 KES 99,056,091.00
Total 61 57 0 4 0 KES 99,056,091.00
All Projects
Browse and filter 61 county development projects
Sub-county Projects: Rachuonyo South
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
61 results
Page 1 of 6