Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
82
Total Projects
80 mapped on GIS
67
Completed
82% completion rate
2
Ongoing
active projects
1K+
Beneficiaries
0K female
KES 0.30B
Approved Budget
283.5% utilized
23
Jobs Created
across all projects
2.44%
Goal Achievement
2 goals met
52M
Total Spent
KES expenditure to date
Status Breakdown
67
Completed
2
Ongoing
3
Stalled
7
Pending
Budget Overview
Cost Estimate
KES 431.7M
Approved
KES 296.7M
Spent
KES 52.3M
Pending Bills
KES 0.0M
Overall utilization
283.5%
Reach & Coverage
1
Sub-Counties
4
Wards Covered
0.5K
Female Beneficiaries
80
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 129.8M
Public Health And Medical Services
KES 85.2M
Roads, Public Works, Transport And Infrastructure
KES 30.9M
Blue Economy, Fisheries, Mining And Digital Economy
KES 5.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 2.7M
Projects by Financial Year
1 financial years tracked
Total: 82
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Homa Bay Town | 82 | 2 | 67 | 0 | 0 | 7 | 3 | 0 | 0 | KES 296,715,747.00 |
| Total | 82 | 2 | 67 | 0 | 0 | 7 | 3 | 0 | 0 | KES 296,715,747.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Homa Bay Arujo | 17 | 0 | 11 | 0 | 0 | 6 | 0 | 0 | 0 | KES 43,998,057.00 |
| Homa Bay Central | 11 | 0 | 11 | 0 | 0 | 0 | 0 | 0 | 0 | KES 16,520,132.00 |
| Homa Bay West | 9 | 0 | 8 | 0 | 0 | 1 | 0 | 0 | 0 | KES 11,500,436.00 |
| Homa Bay East | 5 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | KES 17,480,770.00 |
| Total | 42 | 0 | 35 | 0 | 0 | 7 | 0 | 0 | 0 | KES 89,499,395.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2022/2023 | 82 | 2 | 67 | 0 | 0 | 7 | 3 | 0 | 0 | KES 296,715,747.00 |
| Total | 82 | 2 | 67 | 0 | 0 | 7 | 3 | 0 | 0 | KES 296,715,747.00 |
All Projects
Browse and filter 82 county development projects