Homa Bay County Projects Monitoring Platform
Real-time transparency across 8 sub-counties · 18 wards
0K+
Beneficiaries
0K female
KES 0.06B
Approved Budget
KES 0.00B allocated so far
15
Jobs Created
across all projects
23.81%
Goal Achievement
15 goals met
KES 3.5M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 55.1M
Approved
KES 55.1M
Allocated
KES 3.5M
Utilized
KES 3.5M
Pending Bills
KES 3.5M
Utilization (utilized ÷ allocated)
100%
KES 3.5M of KES 3.5M allocated
Reach & Coverage
8
Sub-Counties
18
Wards Covered
0.0K
Female Beneficiaries
23
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 15.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 13.5M
Public Health And Medical Services
KES 6.0M
Governance, Administration, Communication And Devolution
KES 0.2M
Education, Human Capital Development And Vocational Training
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 63
Project Summary
Every tab adds up to the same 63 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Public Health And Medical Services | 10 | 10 | 0 | 0 | 0 | KES 6,027,356.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 9 | 9 | 0 | 0 | 0 | KES 13,469,595.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 9 | 9 | 0 | 0 | 0 | KES 0.00 |
| Roads, Public Works, Transport And Infrastructure | 5 | 5 | 0 | 0 | 0 | KES 15,016,066.00 |
| Education, Human Capital Development And Vocational Training | 3 | 3 | 0 | 0 | 0 | KES 0.00 |
| Governance, Administration, Communication And Devolution | 2 | 2 | 0 | 0 | 0 | KES 212,800.00 |
| No department assigned | 25 | 25 | 0 | 0 | 0 | KES 20,414,006.00 |
| Total | 63 | 63 | 0 | 0 | 0 | KES 55,139,823.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Ndhiwa | 15 | 15 | 0 | 0 | 0 | KES 4,067,482.00 |
| Rachuonyo North | 12 | 12 | 0 | 0 | 0 | KES 16,074,023.00 |
| Rangwe | 9 | 9 | 0 | 0 | 0 | KES 1,450,000.00 |
| Homa Bay Town | 7 | 7 | 0 | 0 | 0 | KES 6,339,432.00 |
| Rachuonyo South | 6 | 6 | 0 | 0 | 0 | KES 10,062,320.00 |
| Rachuonyo East | 4 | 4 | 0 | 0 | 0 | KES 580,580.00 |
| Suba South | 3 | 3 | 0 | 0 | 0 | KES 4,954,796.00 |
| Suba North | 2 | 2 | 0 | 0 | 0 | KES 1,400,000.00 |
| No sub-county recorded | 5 | 5 | 0 | 0 | 0 | KES 10,211,190.00 |
| Total | 63 | 63 | 0 | 0 | 0 | KES 55,139,823.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| East Gem | 5 | 5 | 0 | 0 | 0 | KES 250,000.00 |
| Kanyadoto | 4 | 4 | 0 | 0 | 0 | KES 2,388,950.00 |
| Kabuoch North | 4 | 4 | 0 | 0 | 0 | KES 369,170.00 |
| Kanyamwa Kalogi | 4 | 4 | 0 | 0 | 0 | KES 1,309,362.00 |
| East Kamagak | 3 | 3 | 0 | 0 | 0 | KES 2,250,000.00 |
| West Kamagak | 2 | 2 | 0 | 0 | 0 | KES 3,750,000.00 |
| Kochia | 2 | 2 | 0 | 0 | 0 | KES 1,200,000.00 |
| Kasgunga | 2 | 2 | 0 | 0 | 0 | KES 1,400,000.00 |
| Gwassi North | 2 | 2 | 0 | 0 | 0 | KES 4,461,300.00 |
| Kanyamwa Kosewe | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Kanyaluo | 2 | 2 | 0 | 0 | 0 | KES 4,586,739.00 |
| West Gem | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Central Karachuonyo | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Kabuoch South | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| Central Kasipul | 1 | 1 | 0 | 0 | 0 | KES 4,062,320.00 |
| Kendu Bay Town | 1 | 1 | 0 | 0 | 0 | KES 1,717,760.00 |
| Ruma Kaksingri | 1 | 1 | 0 | 0 | 0 | KES 493,496.00 |
| Kibiri | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| Homa Bay Town – Sub-county-wide (no ward) | 7 | 7 | 0 | 0 | 0 | KES 6,339,432.00 |
| Rachuonyo North – Sub-county-wide (no ward) | 6 | 6 | 0 | 0 | 0 | KES 9,769,524.00 |
| Rachuonyo East – Sub-county-wide (no ward) | 4 | 4 | 0 | 0 | 0 | KES 580,580.00 |
| No sub-county or ward recorded | 5 | 5 | 0 | 0 | 0 | KES 10,211,190.00 |
| Total | 63 | 63 | 0 | 0 | 0 | KES 55,139,823.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2018/2019 | 63 | 63 | 0 | 0 | 0 | KES 55,139,823.00 |
| Total | 63 | 63 | 0 | 0 | 0 | KES 55,139,823.00 |
All Projects
Browse and filter 63 county development projects