11
Total Projects
1 mapped on GIS
8
Completed
73% completion rate
0
Ongoing
active projects
1K+
Beneficiaries
0K female
KES 0.04B
Approved Budget
0% utilized
0
Jobs Created
across all projects
81.82%
Goal Achievement
9 goals met
0M
Total Spent
KES expenditure to date
Status Breakdown
8
Completed
3
Pending
Budget Overview
Cost Estimate
KES 36.6M
Approved
KES 36.6M
Spent
KES 0.0M
Pending Bills
KES 30.6M
Overall utilization
0%
Reach & Coverage
2
Sub-Counties
3
Wards Covered
0.0K
Female Beneficiaries
1
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 36.6M
Projects by Financial Year
1 financial years tracked
Total: 11
Project Summary
Project counts by status, plus total money and budget allocated across county locations and departments
| Department | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 11 | 0 | 8 | 0 | 0 | 3 | 0 | 0 | 0 | KES 36,609,930.82 |
| Total | 11 | 0 | 8 | 0 | 0 | 3 | 0 | 0 | 0 | KES 36,609,930.82 |
| Sub-county | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Ndhiwa | 2 | 0 | 1 | 0 | 0 | 1 | 0 | 0 | 0 | KES 3,249,670.00 |
| Rachuonyo South | 1 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Total | 3 | 0 | 1 | 0 | 0 | 2 | 0 | 0 | 0 | KES 3,249,670.00 |
| Ward | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| Kwabwai | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | KES 2,999,670.00 |
| Kabuoch North | 1 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KES 250,000.00 |
| South Kasipul | 1 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | KES 0.00 |
| Total | 3 | 0 | 1 | 0 | 0 | 2 | 0 | 0 | 0 | KES 3,249,670.00 |
| Financial Year | Total Projects | Ongoing | Completed | Pending | Pending | Planned | Stalled | Delayed | Canceled | Total Money |
|---|---|---|---|---|---|---|---|---|---|---|
| FY2015/2016 | 11 | 0 | 8 | 0 | 0 | 3 | 0 | 0 | 0 | KES 36,609,930.82 |
| Total | 11 | 0 | 8 | 0 | 0 | 3 | 0 | 0 | 0 | KES 36,609,930.82 |