Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
3K+
Beneficiaries
2K female
KES 0.06B
Approved Budget
KES 0.01B allocated so far
519
Jobs Created
across all projects
50.85%
Goal Achievement
30 goals met
KES 12.1M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 61.4M
Approved
KES 61.1M
Allocated
KES 12.1M
Utilized
KES 12.1M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 12.1M of KES 12.1M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
1.5K
Female Beneficiaries
55
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 31.0M
Roads, Public Works, Transport And Infrastructure
KES 24.6M
Education, Human Capital Development And Vocational Training
KES 4.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Projects by Financial Year
Latest 8 of 8 years
· 2 with no year
Total: 59
Project Summary
Every tab adds up to the same 59 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 17 | 17 | 0 | 0 | 0 | KES 24,582,905.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 12 | 12 | 0 | 0 | 0 | KES 0.00 |
| Education, Human Capital Development And Vocational Training | 7 | 7 | 0 | 0 | 0 | KES 4,000,000.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 5 | 5 | 0 | 0 | 0 | KES 31,024,000.00 |
| No department assigned | 18 | 18 | 0 | 0 | 0 | KES 1,511,000.00 |
| Total | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
| Total | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Ruma Kaksingri | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
| Total | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2025/2026 | 5 | 5 | 0 | 0 | 0 | KES 3,000,000.00 |
| FY2024/2025 | 10 | 10 | 0 | 0 | 0 | KES 250,000.00 |
| FY2023/2024 | 29 | 29 | 0 | 0 | 0 | KES 17,481,397.00 |
| FY2022/2023 | 8 | 8 | 0 | 0 | 0 | KES 0.00 |
| FY2020/2021 | 2 | 2 | 0 | 0 | 0 | KES 8,869,012.00 |
| FY2018/2019 | 1 | 1 | 0 | 0 | 0 | KES 493,496.00 |
| FY2017/2018 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 1 | 1 | 0 | 0 | 0 | KES 31,024,000.00 |
| No financial year recorded | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Total | 59 | 59 | 0 | 0 | 0 | KES 61,117,905.00 |
All Projects
Browse and filter 59 county development projects