Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
2K+
Beneficiaries
1K female
KES 0.11B
Approved Budget
KES 0.02B allocated so far
240
Jobs Created
across all projects
33.33%
Goal Achievement
13 goals met
KES 19.1M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 111.4M
Approved
KES 110.9M
Allocated
KES 19.1M
Utilized
KES 19.1M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 19.1M of KES 19.1M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
1.2K
Female Beneficiaries
37
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 86.6M
Roads, Public Works, Transport And Infrastructure
KES 20.3M
Public Health And Medical Services
KES 3.5M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Department Of Agriculture, Irrigation And Livestock Development
KES 0.0M
Projects by Financial Year
Latest 7 of 7 years
Total: 39
Project Summary
Every tab adds up to the same 39 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 9 | 9 | 0 | 0 | 0 | KES 20,257,037.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 9 | 9 | 0 | 0 | 0 | KES 86,640,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 7 | 7 | 0 | 0 | 0 | KES 0.00 |
| Department Of Agriculture, Irrigation And Livestock Development | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| Public Health And Medical Services | 1 | 1 | 0 | 0 | 0 | KES 3,500,000.00 |
| No department assigned | 10 | 10 | 0 | 0 | 0 | KES 500,000.00 |
| Total | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
| Total | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Gwassi South | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
| Total | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2025/2026 | 4 | 4 | 0 | 0 | 0 | KES 79,990,000.00 |
| FY2024/2025 | 9 | 9 | 0 | 0 | 0 | KES 11,079,021.00 |
| FY2023/2024 | 12 | 12 | 0 | 0 | 0 | KES 10,400,000.00 |
| FY2022/2023 | 6 | 6 | 0 | 0 | 0 | KES 9,428,016.00 |
| FY2019/2020 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2017/2018 | 3 | 3 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 4 | 4 | 0 | 0 | 0 | KES 0.00 |
| Total | 39 | 39 | 0 | 0 | 0 | KES 110,897,037.00 |
All Projects
Browse and filter 39 county development projects