Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
12K+
Beneficiaries
0K female
KES 0.03B
Approved Budget
KES 0.02B allocated so far
359
Jobs Created
across all projects
52.63%
Goal Achievement
20 goals met
KES 15.6M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 28.2M
Approved
KES 28.2M
Allocated
KES 15.6M
Utilized
KES 15.6M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 15.6M of KES 15.6M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.3K
Female Beneficiaries
34
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 11.2M
Education, Human Capital Development And Vocational Training
KES 10.2M
Roads, Public Works, Transport And Infrastructure
KES 4.4M
Public Health And Medical Services
KES 1.2M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.5M
Projects by Financial Year
Latest 7 of 7 years
Total: 38
Project Summary
Every tab adds up to the same 38 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 12 | 12 | 0 | 0 | 0 | KES 11,151,765.00 |
| Education, Human Capital Development And Vocational Training | 9 | 9 | 0 | 0 | 0 | KES 10,185,670.00 |
| Roads, Public Works, Transport And Infrastructure | 6 | 6 | 0 | 0 | 0 | KES 4,447,840.00 |
| Public Health And Medical Services | 5 | 5 | 0 | 0 | 0 | KES 1,160,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 2 | 2 | 0 | 0 | 0 | KES 499,100.00 |
| No department assigned | 4 | 4 | 0 | 0 | 0 | KES 750,000.00 |
| Total | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba North | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
| Total | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Lambwe | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
| Total | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 4 | 4 | 0 | 0 | 0 | KES 4,000,000.00 |
| FY2023/2024 | 18 | 18 | 0 | 0 | 0 | KES 12,447,285.00 |
| FY2022/2023 | 11 | 11 | 0 | 0 | 0 | KES 6,139,250.00 |
| FY2021/2022 | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| FY2020/2021 | 2 | 2 | 0 | 0 | 0 | KES 4,447,840.00 |
| FY2019/2020 | 1 | 1 | 0 | 0 | 0 | KES 870,000.00 |
| FY2014/2015 | 1 | 1 | 0 | 0 | 0 | KES 290,000.00 |
| Total | 38 | 38 | 0 | 0 | 0 | KES 28,194,375.00 |
All Projects
Browse and filter 38 county development projects