Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 0 wards
0K+
Beneficiaries
0K female
KES 0.03B
Approved Budget
KES 0.00B allocated so far
0
Jobs Created
across all projects
0%
Goal Achievement
0 goals met
KES 0.0M
Budget Utilized
0% of allocated
Budget Overview
Cost Estimate
KES 19.6M
Approved
KES 30.0M
Allocated
KES 0.0M
Utilized
KES 0.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 0.0M allocated
Reach & Coverage
1
Sub-Counties
0
Wards Covered
0.0K
Female Beneficiaries
18
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 18.0M
Education, Human Capital Development And Vocational Training
KES 12.0M
Public Health And Medical Services
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 18
Project Summary
Every tab adds up to the same 18 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Education, Human Capital Development And Vocational Training | 12 | 0 | 12 | 0 | 0 | KES 12,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 5 | 0 | 5 | 0 | 0 | KES 18,017,254.00 |
| Public Health And Medical Services | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| Total | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo East | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Total | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo East – Sub-county-wide (no ward) | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Total | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
| Total | 18 | 0 | 18 | 0 | 0 | KES 30,017,254.00 |
All Projects
Browse and filter 18 county development projects