Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
2K+
Beneficiaries
1K female
KES 0.01B
Approved Budget
KES 0.01B allocated so far
302
Jobs Created
across all projects
56.25%
Goal Achievement
18 goals met
KES 9.5M
Budget Utilized
100% of allocated
Status Breakdown
Adds up to all 32 projects
Budget Overview
Cost Estimate KES 15.3M
Approved KES 14.8M
Allocated KES 9.5M
Utilized KES 9.5M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 9.5M of KES 9.5M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
0.6K
Female Beneficiaries
32
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 10.8M
Blue Economy, Fisheries, Mining And Digital Economy
KES 2.5M
Education, Human Capital Development And Vocational Training
KES 1.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Department Of Agriculture, Irrigation And Livestock Development
KES 0.0M
Projects by Financial Year
24/25
Latest 1 of 1 years Total: 32
Project Summary
Every tab adds up to the same 32 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Roads, Public Works, Transport And Infrastructure 7 7 0 0 0 KES 10,829,021.00
Education, Human Capital Development And Vocational Training 7 7 0 0 0 KES 1,000,000.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 4 4 0 0 0 KES 0.00
Blue Economy, Fisheries, Mining And Digital Economy 3 3 0 0 0 KES 2,482,000.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 2 2 0 0 0 KES 0.00
Department Of Agriculture, Irrigation And Livestock Development 1 1 0 0 0 KES 0.00
No department assigned 8 8 0 0 0 KES 500,000.00
Total 32 32 0 0 0 KES 14,811,021.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Suba South 32 32 0 0 0 KES 14,811,021.00
Total 32 32 0 0 0 KES 14,811,021.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Ruma Kaksingri 10 10 0 0 0 KES 250,000.00
Gwassi South 9 9 0 0 0 KES 11,079,021.00
Kaksingri West 9 9 0 0 0 KES 1,000,000.00
Gwassi North 4 4 0 0 0 KES 2,482,000.00
Total 32 32 0 0 0 KES 14,811,021.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2024/2025 32 32 0 0 0 KES 14,811,021.00
Total 32 32 0 0 0 KES 14,811,021.00
All Projects
Browse and filter 32 county development projects
Sub-county Projects: Suba South
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
32 results
Page 1 of 3