Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
2K+
Beneficiaries
1K female
KES 0.01B
Approved Budget
KES 0.01B allocated so far
302
Jobs Created
across all projects
56.25%
Goal Achievement
18 goals met
KES 9.5M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 15.3M
Approved
KES 14.8M
Allocated
KES 9.5M
Utilized
KES 9.5M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 9.5M of KES 9.5M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
0.6K
Female Beneficiaries
32
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 10.8M
Blue Economy, Fisheries, Mining And Digital Economy
KES 2.5M
Education, Human Capital Development And Vocational Training
KES 1.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Department Of Agriculture, Irrigation And Livestock Development
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 32
Project Summary
Every tab adds up to the same 32 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 7 | 7 | 0 | 0 | 0 | KES 10,829,021.00 |
| Education, Human Capital Development And Vocational Training | 7 | 7 | 0 | 0 | 0 | KES 1,000,000.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 4 | 4 | 0 | 0 | 0 | KES 0.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 3 | 3 | 0 | 0 | 0 | KES 2,482,000.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Department Of Agriculture, Irrigation And Livestock Development | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| No department assigned | 8 | 8 | 0 | 0 | 0 | KES 500,000.00 |
| Total | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba South | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
| Total | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Ruma Kaksingri | 10 | 10 | 0 | 0 | 0 | KES 250,000.00 |
| Gwassi South | 9 | 9 | 0 | 0 | 0 | KES 11,079,021.00 |
| Kaksingri West | 9 | 9 | 0 | 0 | 0 | KES 1,000,000.00 |
| Gwassi North | 4 | 4 | 0 | 0 | 0 | KES 2,482,000.00 |
| Total | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
| Total | 32 | 32 | 0 | 0 | 0 | KES 14,811,021.00 |
All Projects
Browse and filter 32 county development projects