Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 1 wards
7K+
Beneficiaries
1K female
KES 0.02B
Approved Budget
KES 0.01B allocated so far
252
Jobs Created
across all projects
68.75%
Goal Achievement
11 goals met
KES 13.9M
Budget Utilized
100% of allocated
Budget Overview
Cost Estimate
KES 15.9M
Approved
KES 15.0M
Allocated
KES 13.9M
Utilized
KES 13.9M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
100%
KES 13.9M of KES 13.9M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.7K
Female Beneficiaries
16
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 4.4M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 4.2M
Blue Economy, Fisheries, Mining And Digital Economy
KES 3.3M
Education, Human Capital Development And Vocational Training
KES 3.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.1M
Projects by Financial Year
Latest 1 of 1 years
Total: 16
Project Summary
Every tab adds up to the same 16 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 6 | 6 | 0 | 0 | 0 | KES 4,150,000.00 |
| Education, Human Capital Development And Vocational Training | 4 | 4 | 0 | 0 | 0 | KES 3,000,000.00 |
| Blue Economy, Fisheries, Mining And Digital Economy | 3 | 3 | 0 | 0 | 0 | KES 3,342,691.00 |
| Roads, Public Works, Transport And Infrastructure | 1 | 1 | 0 | 0 | 0 | KES 4,408,071.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | KES 100,000.00 |
| Public Health And Medical Services | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| Total | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba North | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Total | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rusinga Island | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Total | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2023/2024 | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
| Total | 16 | 16 | 0 | 0 | 0 | KES 15,000,762.00 |
All Projects
Browse and filter 16 county development projects