Real-time transparency across 1 sub-counties · 4 wards
8K+
Beneficiaries
5K female
KES 0.06B
Approved Budget
KES 0.02B allocated so far
306
Jobs Created
across all projects
22.41%
Goal Achievement
13 goals met
KES 15.4M
Budget Utilized
99.58% of allocated
Status Breakdown
Adds up to all 58 projects
Budget Overview
Cost Estimate KES 63.8M
Approved KES 63.8M
Allocated KES 15.5M
Utilized KES 15.4M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
99.58%
KES 15.4M of KES 15.5M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
5.1K
Female Beneficiaries
58
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 26.6M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 19.0M
Education, Human Capital Development And Vocational Training
KES 12.0M
Public Health And Medical Services
KES 3.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.3M
Projects by Financial Year
23/24
Latest 1 of 1 years Total: 58
Project Summary
Every tab adds up to the same 58 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Water, Sanitation, Environment, Energy, Forestry And Climate Change 16 16 0 0 0 KES 18,950,000.00
Education, Human Capital Development And Vocational Training 15 15 0 0 0 KES 12,000,000.00
Roads, Public Works, Transport And Infrastructure 13 13 0 0 0 KES 26,615,904.00
Public Health And Medical Services 2 2 0 0 0 KES 3,000,000.00
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 1 1 0 0 0 KES 250,000.00
No department assigned 11 11 0 0 0 KES 2,990,950.00
Total 58 58 0 0 0 KES 63,806,854.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Rachuonyo East 58 58 0 0 0 KES 63,806,854.00
Total 58 58 0 0 0 KES 63,806,854.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Kojwach 4 4 0 0 0 KES 4,050,000.00
Kabondo West 3 3 0 0 0 KES 3,800,000.00
Kokwanyo/Kakelo 3 3 0 0 0 KES 3,800,000.00
Kabondo East 3 3 0 0 0 KES 3,800,000.00
Rachuonyo East – Sub-county-wide (no ward) 45 45 0 0 0 KES 48,356,854.00
Total 58 58 0 0 0 KES 63,806,854.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2023/2024 58 58 0 0 0 KES 63,806,854.00
Total 58 58 0 0 0 KES 63,806,854.00
All Projects
Browse and filter 58 county development projects
Sub-county Projects: Rachuonyo East
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
58 results
Page 1 of 5