Homa Bay County Projects Monitoring Platform
Real-time transparency across 5 sub-counties · 9 wards
3K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.01B allocated so far
213
Jobs Created
across all projects
22.22%
Goal Achievement
4 goals met
KES 8.1M
Budget Utilized
132.83% of allocated
Status Breakdown
Adds up to all 18 projects
Budget Overview
Cost Estimate KES 19.9M
Approved KES 19.9M
Allocated KES 6.1M
Utilized KES 8.1M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
132.83%
KES 8.1M of KES 6.1M allocated
Reach & Coverage
5
Sub-Counties
9
Wards Covered
0.0K
Female Beneficiaries
18
GIS Mapped
View on GIS Map
Top Departments by Investment
Blue Economy, Fisheries, Mining And Digital Economy
KES 19.9M
Projects by Financial Year
23/24
Latest 1 of 1 years Total: 18
Project Summary
Every tab adds up to the same 18 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Blue Economy, Fisheries, Mining And Digital Economy 18 18 0 0 0 KES 19,857,025.00
Total 18 18 0 0 0 KES 19,857,025.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Suba North 7 7 0 0 0 KES 7,030,652.00
Rangwe 5 5 0 0 0 KES 5,897,596.00
Homa Bay Town 3 3 0 0 0 KES 6,928,777.00
Rachuonyo North 2 2 0 0 0 KES 0.00
Rachuonyo South 1 1 0 0 0 KES 0.00
Total 18 18 0 0 0 KES 19,857,025.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Kochia 5 5 0 0 0 KES 5,897,596.00
Rusinga Island 3 3 0 0 0 KES 3,342,691.00
Kasgunga 2 2 0 0 0 KES 2,937,961.00
Mfangano Island 2 2 0 0 0 KES 750,000.00
Central Karachuonyo 1 1 0 0 0 KES 0.00
West Karachuonyo 1 1 0 0 0 KES 0.00
Homa Bay East 1 1 0 0 0 KES 3,000,000.00
Homa Bay Arujo 1 1 0 0 0 KES 1,000,000.00
West Kamagak 1 1 0 0 0 KES 0.00
Homa Bay Town – Sub-county-wide (no ward) 1 1 0 0 0 KES 2,928,777.00
Total 18 18 0 0 0 KES 19,857,025.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2023/2024 18 18 0 0 0 KES 19,857,025.00
Total 18 18 0 0 0 KES 19,857,025.00
All Projects
Browse and filter 18 county development projects
Department Projects: Blue Economy, Fisheries, Mining And Digital Economy
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
18 results
Page 1 of 2