Homa Bay County Projects Monitoring Platform
Real-time transparency across 5 sub-counties · 9 wards
6K+
Beneficiaries
2K female
KES 0.00B
Approved Budget
KES 0.00B allocated so far
295
Jobs Created
across all projects
77.78%
Goal Achievement
14 goals met
KES 4.9M
Budget Utilized
125.66% of allocated
Status Breakdown
Adds up to all 18 projects
Budget Overview
Cost Estimate KES 5.9M
Approved KES 5.0M
Allocated KES 3.9M
Utilized KES 4.9M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
125.66%
KES 4.9M of KES 3.9M allocated
Reach & Coverage
5
Sub-Counties
9
Wards Covered
1.8K
Female Beneficiaries
18
GIS Mapped
View on GIS Map
Top Departments by Investment
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 5.0M
Projects by Financial Year
23/24
Latest 1 of 1 years Total: 18
Project Summary
Every tab adds up to the same 18 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives 18 18 0 0 0 KES 4,992,531.00
Total 18 18 0 0 0 KES 4,992,531.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Suba North 7 7 0 0 0 KES 1,849,182.00
Suba South 5 5 0 0 0 KES 0.00
Homa Bay Town 3 3 0 0 0 KES 1,747,489.00
Rachuonyo South 1 1 0 0 0 KES 150,000.00
Rachuonyo East 1 1 0 0 0 KES 250,000.00
No sub-county recorded 1 1 0 0 0 KES 995,860.00
Total 18 18 0 0 0 KES 4,992,531.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Ruma Kaksingri 5 5 0 0 0 KES 0.00
Mfangano Island 3 3 0 0 0 KES 749,182.00
Homa Bay Arujo 2 2 0 0 0 KES 1,497,480.00
Gembe 2 2 0 0 0 KES 750,000.00
West Kamagak 1 1 0 0 0 KES 150,000.00
Lambwe 1 1 0 0 0 KES 250,000.00
Kojwach 1 1 0 0 0 KES 250,000.00
Homa Bay East 1 1 0 0 0 KES 250,009.00
Rusinga Island 1 1 0 0 0 KES 100,000.00
No sub-county or ward recorded 1 1 0 0 0 KES 995,860.00
Total 18 18 0 0 0 KES 4,992,531.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2023/2024 18 18 0 0 0 KES 4,992,531.00
Total 18 18 0 0 0 KES 4,992,531.00
All Projects
Browse and filter 18 county development projects
Department Projects: Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
18 results
Page 1 of 2