Budget Overview
Cost Estimate
KES 17.3M
Approved
KES 17.3M
Allocated
KES 0.0M
Utilized
KES 0.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 0.0M allocated
Reach & Coverage
1
Sub-Counties
1
Wards Covered
0.0K
Female Beneficiaries
11
GIS Mapped
Top Departments by Investment
Public Health And Medical Services
KES 7.5M
Roads, Public Works, Transport And Infrastructure
KES 5.6M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 3.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 11
Project Summary
Every tab adds up to the same 11 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 3 | 3 | 0 | 0 | 0 | KES 5,577,949.00 |
| Public Health And Medical Services | 3 | 3 | 0 | 0 | 0 | KES 7,500,000.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 1 | 1 | 0 | 0 | 0 | KES 3,000,000.00 |
| No department assigned | 4 | 4 | 0 | 0 | 0 | KES 1,250,000.00 |
| Total | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo South | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Total | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| West Kasipul | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Total | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2022/2023 | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |
| Total | 11 | 11 | 0 | 0 | 0 | KES 17,327,949.00 |