Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 4 wards
1K+
Beneficiaries
0K female
KES 0.04B
Approved Budget
KES 0.00B allocated so far
160
Jobs Created
across all projects
2.13%
Goal Achievement
1 goals met
KES 0.0M
Budget Utilized
0% of allocated
Status Breakdown
Adds up to all 47 projects
Budget Overview
Cost Estimate KES 44.9M
Approved KES 44.9M
Allocated KES 5.0M
Utilized KES 0.0M
Pending Bills KES 0.0M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 5.0M allocated
Reach & Coverage
1
Sub-Counties
4
Wards Covered
0.0K
Female Beneficiaries
46
GIS Mapped
View on GIS Map
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 30.6M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 9.1M
Education, Human Capital Development And Vocational Training
KES 2.1M
Public Health And Medical Services
KES 0.0M
Projects by Financial Year
22/23
Latest 1 of 1 years Total: 47
Project Summary
Every tab adds up to the same 47 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
Department Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Roads, Public Works, Transport And Infrastructure 24 24 0 0 0 KES 30,642,832.00
Water, Sanitation, Environment, Energy, Forestry And Climate Change 8 8 0 0 0 KES 9,105,100.00
Public Health And Medical Services 3 3 0 0 0 KES 0.00
Education, Human Capital Development And Vocational Training 1 1 0 0 0 KES 2,052,330.00
No department assigned 11 11 0 0 0 KES 3,094,364.00
Total 47 47 0 0 0 KES 44,894,626.00
Sub-county Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Rangwe 47 47 0 0 0 KES 44,894,626.00
Total 47 47 0 0 0 KES 44,894,626.00
Ward Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
Kochia 20 20 0 0 0 KES 24,021,284.00
East Gem 11 11 0 0 0 KES 10,570,246.00
West Gem 9 9 0 0 0 KES 2,457,008.00
Kagan 1 1 0 0 0 KES 0.00
Rangwe – Sub-county-wide (no ward) 6 6 0 0 0 KES 7,846,088.00
Total 47 47 0 0 0 KES 44,894,626.00
Financial Year Total Projects Completed Ongoing Stalled / Delayed Planned / Pending Total Money
FY2022/2023 47 47 0 0 0 KES 44,894,626.00
Total 47 47 0 0 0 KES 44,894,626.00
All Projects
Browse and filter 47 county development projects
Sub-county Projects: Rangwe
These projects were opened from the summary table. Click any project card title or View button to open the project details page.
Clear drill-down
Loading…
47 results
Page 1 of 4