Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 5 wards
0K+
Beneficiaries
0K female
KES 0.04B
Approved Budget
KES 0.00B allocated so far
23
Jobs Created
across all projects
8.33%
Goal Achievement
1 goals met
KES 0.0M
Budget Utilized
0% of allocated
Budget Overview
Cost Estimate
KES 35.7M
Approved
KES 35.7M
Allocated
KES 0.3M
Utilized
KES 0.0M
Pending Bills
KES 0.3M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 0.3M allocated
Reach & Coverage
1
Sub-Counties
5
Wards Covered
0.0K
Female Beneficiaries
1
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 35.1M
Public Health And Medical Services
KES 0.6M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 12
Project Summary
Every tab adds up to the same 12 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 5 | 5 | 0 | 0 | 0 | KES 35,143,788.00 |
| Public Health And Medical Services | 3 | 3 | 0 | 0 | 0 | KES 597,573.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | KES 0.00 |
| No department assigned | 3 | 3 | 0 | 0 | 0 | KES 0.00 |
| Total | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Suba North | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
| Total | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rusinga Island | 3 | 3 | 0 | 0 | 0 | KES 22,249,141.00 |
| Mfangano Island | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Kasgunga | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Lambwe | 2 | 2 | 0 | 0 | 0 | KES 4,447,840.00 |
| Gembe | 2 | 2 | 0 | 0 | 0 | KES 8,754,380.00 |
| Suba North – Sub-county-wide (no ward) | 1 | 1 | 0 | 0 | 0 | KES 290,000.00 |
| Total | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2020/2021 | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
| Total | 12 | 12 | 0 | 0 | 0 | KES 35,741,361.00 |
All Projects
Browse and filter 12 county development projects