Homa Bay County Projects Monitoring Platform
Real-time transparency across 1 sub-counties · 3 wards
0K+
Beneficiaries
0K female
KES 0.00B
Approved Budget
KES 0.00B allocated so far
0
Jobs Created
across all projects
0%
Goal Achievement
0 goals met
KES 0.0M
Budget Utilized
0% of allocated
Budget Overview
Cost Estimate
KES 6.1M
Approved
KES 3.7M
Allocated
KES 0.0M
Utilized
KES 0.0M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 0.0M allocated
Reach & Coverage
1
Sub-Counties
3
Wards Covered
0.0K
Female Beneficiaries
0
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 3.7M
Public Health And Medical Services
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 7
Project Summary
Every tab adds up to the same 7 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Public Health And Medical Services | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 2 | 2 | 0 | 0 | 0 | KES 3,718,600.00 |
| No department assigned | 3 | 3 | 0 | 0 | 0 | KES 0.00 |
| Total | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rachuonyo South | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
| Total | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| West Kasipul | 3 | 3 | 0 | 0 | 0 | KES 746,125.00 |
| Central Kasipul | 2 | 2 | 0 | 0 | 0 | KES 2,972,475.00 |
| South Kasipul | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| Total | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2019/2020 | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
| Total | 7 | 7 | 0 | 0 | 0 | KES 3,718,600.00 |
All Projects
Browse and filter 7 county development projects