Budget Overview
Cost Estimate
KES 88.3M
Approved
KES 88.3M
Allocated
KES 88.3M
Utilized
KES 0.0M
Pending Bills
KES 86.5M
Utilization (utilized ÷ allocated)
0%
KES 0.0M of KES 88.3M allocated
Reach & Coverage
5
Sub-Counties
3
Wards Covered
0.0K
Female Beneficiaries
0
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 88.3M
Projects by Financial Year
Latest 1 of 1 years
Total: 26
Project Summary
Every tab adds up to the same 26 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |
| Total | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Rangwe | 1 | 1 | 0 | 0 | 0 | KES 7,008,720.00 |
| Ndhiwa | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Suba North | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Homa Bay Town | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Rachuonyo East | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| No sub-county recorded | 21 | 21 | 0 | 0 | 0 | KES 81,255,005.60 |
| Total | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Kagan | 1 | 1 | 0 | 0 | 0 | KES 7,008,720.00 |
| Kanyamwa Kosewe | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Rusinga Island | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Homa Bay Town – Sub-county-wide (no ward) | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Rachuonyo East – Sub-county-wide (no ward) | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| No sub-county or ward recorded | 21 | 21 | 0 | 0 | 0 | KES 81,255,005.60 |
| Total | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2014/2015 | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |
| Total | 26 | 22 | 0 | 0 | 4 | KES 88,263,725.60 |