Homa Bay County Projects Monitoring Platform
Real-time transparency across 0 sub-counties · 0 wards
0K+
Beneficiaries
0K female
KES 0.02B
Approved Budget
KES 0.02B allocated so far
0
Jobs Created
across all projects
1.69%
Goal Achievement
1 goals met
KES 0.2M
Budget Utilized
0.77% of allocated
Budget Overview
Cost Estimate
KES 30.7M
Approved
KES 21.4M
Allocated
KES 19.5M
Utilized
KES 0.2M
Pending Bills
KES 19.4M
Utilization (utilized ÷ allocated)
0.77%
KES 0.2M of KES 19.5M allocated
Reach & Coverage
0
Sub-Counties
0
Wards Covered
0.0K
Female Beneficiaries
41
GIS Mapped
Top Departments by Investment
Roads, Public Works, Transport And Infrastructure
KES 13.4M
Public Health And Medical Services
KES 8.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 0.0M
Education, Human Capital Development And Vocational Training
KES 0.0M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 0.0M
Projects by Financial Year
Latest 8 of 8 years
· 29 with no year
Total: 59
Project Summary
Every tab adds up to the same 59 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 10 | 0 | 10 | 0 | 0 | KES 13,412,848.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 3 | 0 | 3 | 0 | 0 | KES 0.00 |
| Public Health And Medical Services | 2 | 0 | 2 | 0 | 0 | KES 7,978,354.40 |
| Education, Human Capital Development And Vocational Training | 2 | 0 | 2 | 0 | 0 | KES 0.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| No department assigned | 41 | 0 | 41 | 0 | 0 | KES 0.00 |
| Total | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| No sub-county recorded | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
| Total | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| No sub-county or ward recorded | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
| Total | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2025/2026 | 6 | 0 | 6 | 0 | 0 | KES 0.00 |
| FY2024/2025 | 8 | 0 | 8 | 0 | 0 | KES 0.00 |
| FY2023/2024 | 8 | 0 | 8 | 0 | 0 | KES 0.00 |
| FY2022/2023 | 4 | 0 | 4 | 0 | 0 | KES 0.00 |
| FY2020/2021 | 1 | 0 | 1 | 0 | 0 | KES 13,412,848.00 |
| FY2019/2020 | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| FY2014/2015 | 1 | 0 | 1 | 0 | 0 | KES 5,978,396.40 |
| FY2012/2013 | 1 | 0 | 1 | 0 | 0 | KES 0.00 |
| No financial year recorded | 29 | 0 | 29 | 0 | 0 | KES 1,999,958.00 |
| Total | 59 | 0 | 59 | 0 | 0 | KES 21,391,202.40 |
All Projects
Browse and filter 59 county development projects