Homa Bay County Projects Monitoring Platform
Real-time transparency across 0 sub-counties · 0 wards
15K+
Beneficiaries
7K female
KES 1.28B
Approved Budget
KES 1.04B allocated so far
540
Jobs Created
across all projects
68.95%
Goal Achievement
131 goals met
KES 82.7M
Budget Utilized
7.96% of allocated
Budget Overview
Cost Estimate
KES 1,282.4M
Approved
KES 1,275.3M
Allocated
KES 1,039.3M
Utilized
KES 82.7M
Pending Bills
KES 949.2M
Utilization (utilized ÷ allocated)
7.96%
KES 82.7M of KES 1,039.3M allocated
Reach & Coverage
0
Sub-Counties
0
Wards Covered
7.0K
Female Beneficiaries
29
GIS Mapped
Top Departments by Investment
Public Health And Medical Services
KES 832.6M
Roads, Public Works, Transport And Infrastructure
KES 252.5M
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 128.6M
Education, Human Capital Development And Vocational Training
KES 35.4M
Governance, Administration, Communication And Devolution
KES 13.7M
Projects by Financial Year
Latest 8 of 12 years
· 3 with no year
Total: 190
Project Summary
Every tab adds up to the same 190 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| Roads, Public Works, Transport And Infrastructure | 58 | 58 | 0 | 0 | 0 | KES 252,489,552.12 |
| Public Health And Medical Services | 56 | 56 | 0 | 0 | 0 | KES 832,572,351.00 |
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 38 | 38 | 0 | 0 | 0 | KES 128,644,430.42 |
| Education, Human Capital Development And Vocational Training | 15 | 15 | 0 | 0 | 0 | KES 35,397,693.61 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 9 | 9 | 0 | 0 | 0 | KES 7,399,136.00 |
| Governance, Administration, Communication And Devolution | 4 | 4 | 0 | 0 | 0 | KES 13,665,721.99 |
| Finance And Economic Planning | 2 | 2 | 0 | 0 | 0 | KES 2,036,540.40 |
| Office Of The County Secretary And Head Of Public Service | 1 | 1 | 0 | 0 | 0 | KES 555,000.00 |
| No department assigned | 7 | 7 | 0 | 0 | 0 | KES 2,571,973.00 |
| Total | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| No sub-county recorded | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
| Total | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| No sub-county or ward recorded | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
| Total | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Total Money |
|---|---|---|---|---|---|---|
| FY2024/2025 | 3 | 3 | 0 | 0 | 0 | KES 8,243,418.00 |
| FY2023/2024 | 26 | 26 | 0 | 0 | 0 | KES 82,395,760.00 |
| FY2022/2023 | 6 | 6 | 0 | 0 | 0 | KES 11,415,078.00 |
| FY2021/2022 | 12 | 12 | 0 | 0 | 0 | KES 151,810,226.00 |
| FY2020/2021 | 40 | 40 | 0 | 0 | 0 | KES 130,770,082.52 |
| FY2019/2020 | 13 | 13 | 0 | 0 | 0 | KES 16,954,224.00 |
| FY2018/2019 | 5 | 5 | 0 | 0 | 0 | KES 10,211,190.00 |
| FY2017/2018 | 2 | 2 | 0 | 0 | 0 | KES 0.00 |
| FY2016/2017 | 2 | 2 | 0 | 0 | 0 | KES 3,508,530.00 |
| FY2015/2016 | 13 | 13 | 0 | 0 | 0 | KES 58,109,536.91 |
| FY2014/2015 | 57 | 57 | 0 | 0 | 0 | KES 742,976,325.91 |
| FY2013/2014 | 8 | 8 | 0 | 0 | 0 | KES 53,408,976.20 |
| No financial year recorded | 3 | 3 | 0 | 0 | 0 | KES 5,529,051.00 |
| Total | 190 | 190 | 0 | 0 | 0 | KES 1,275,332,398.54 |
All Projects
Browse and filter 190 county development projects