Homa Bay County Projects Monitoring Platform
Real-time transparency across 0 sub-counties · 0 wards
12K+
Beneficiaries
7K female
KES 0.08B
Approved Budget
KES 0.08B allocated so far
540
Jobs Created
across all projects
46.34%
Goal Achievement
19 goals met
KES 82.6M
Budget Utilized
99.83% of allocated
Budget Overview
Cost Estimate
KES 87.0M
Approved
KES 83.4M
Allocated
KES 82.7M
Utilized
KES 82.6M
Pending Bills
KES 0.0M
Utilization (utilized ÷ allocated)
99.83%
KES 82.6M of KES 82.7M allocated
Reach & Coverage
0
Sub-Counties
0
Wards Covered
7.0K
Female Beneficiaries
29
GIS Mapped
Top Departments by Investment
Water, Sanitation, Environment, Energy, Forestry And Climate Change
KES 79.1M
Education, Human Capital Development And Vocational Training
KES 2.0M
Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives
KES 1.0M
Public Health And Medical Services
KES 0.3M
Roads, Public Works, Transport And Infrastructure
KES 0.0M
Projects by Financial Year
Latest 1 of 1 years
Total: 41
Project Summary
Every tab adds up to the same 41 projects. Projects missing a department, location or year are listed in a “not recorded” row at the bottom.
| Department | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| Water, Sanitation, Environment, Energy, Forestry And Climate Change | 22 | 20 | 1 | 0 | 0 | 1 | KES 79,078,219.00 |
| Education, Human Capital Development And Vocational Training | 4 | 2 | 1 | 0 | 0 | 1 | KES 2,000,000.00 |
| Roads, Public Works, Transport And Infrastructure | 2 | 1 | 0 | 0 | 0 | 1 | KES 0.00 |
| Trade, Investments, Industrialization, Tourism, Marketing, Youth Affairs And Cooperatives | 1 | 1 | 0 | 0 | 0 | 0 | KES 995,860.00 |
| Public Health And Medical Services | 1 | 1 | 0 | 0 | 0 | 0 | KES 321,681.00 |
| No department assigned | 11 | 1 | 6 | 0 | 0 | 4 | KES 995,860.00 |
| Total | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Sub-county | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| No sub-county recorded | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Total | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Ward | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| No sub-county or ward recorded | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Total | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Financial Year | Total Projects | Completed | Ongoing | Stalled / Delayed | Planned / Pending | Not set | Total Money |
|---|---|---|---|---|---|---|---|
| FY2023/2024 | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
| Total | 41 | 26 | 8 | 0 | 0 | 7 | KES 83,391,620.00 |
All Projects
Browse and filter 41 county development projects