Completed
Wanyama - Temo - Wakondo -Luore road
Approved Budget
KES 7.79M
Location
Rusinga Island · Suba North
Financial Year
FY2022/2023
Category
Option 2
Funding Source
County Government
Budget Utilization
100%Approved
KES 7.79M
Total budget
Utilized
KES 7.79M
Amount spent
Balance
KES 0.00M
Remaining
100% of budget absorbed
100.00% disbursed
Impact & Beneficiaries
0
Female
0
Male
650
Total
32
Jobs Created
Goal Achieved
Project Details
Project Code
—
Sector
Energy Infrastructure and ICT (EII)
Implementing Agency
Roads Public Works Transport And Infra
Department
Roads, Public Works, Transport And Infrastructure
Sub-County / Ward
Suba North / Rusinga Island
Funding Source
County Government
Financial Breakdown
Funds Available (This Year)
KES 7,790,096
Amount Allocated
KES 7,790,096
Total Disbursed to 30 June
KES 7,790,096
Expenditure to Date
KES 7,790,096
Project Balance
KES 0
Disbursed % of Approved
100.00%
Goal & Expected Output
Project Goal
To create access for the community along the road
Expected Output
Creation of job opportunities
Project Description
Opening of Wanyama- Temo - Wakondo- Luore road
Project Location
-0.3857630, 34.1794480
Community Feedback
No public feedback yet.
Be the first to share your thoughts.
County Support
Hotline
0800 000 889
Email
Office Hours
Mon–Fri, 8AM–5PM
HQ
County Headquarters, Homa Bay, Arujo